SENATE FINANCE COMMITTEE SUBSTITUTE FOR

SENATE BILL 246

56th legislature - STATE OF NEW MEXICO - second session, 2024

 

 

 

 

 

 

 

AN ACT

RELATING TO CAPITAL EXPENDITURES; REAUTHORIZING OR REAPPROPRIATING BALANCES, EXPANDING OR CHANGING PURPOSES, EXTENDING EXPENDITURE PERIODS, CHANGING AGENCIES AND ESTABLISHING CONDITIONS FOR THE REVERSION OR TRANSFER OF UNEXPENDED BALANCES OF APPROPRIATIONS MADE BY THE LEGISLATURE IN PRIOR YEARS; DECLARING AN EMERGENCY.

 

BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF NEW MEXICO:

     SECTION 1. SEVERANCE TAX BONDS--REVERSION OF PROCEEDS.--

          A. Except as otherwise provided in another section of this act:

                (1) the unexpended balance from the proceeds of severance tax bonds issued for a project that has been reauthorized in this act shall revert to the severance tax bonding fund:

                     (a) at the end of the expenditure period as set forth in this act, if the expenditure period is changed in this act; or

                     (b) if the expenditure period is not changed in this act, pursuant to the time frame set forth in the law that originally authorized the severance tax bonds or the time frame set forth in any law that has previously reauthorized the expenditure of the proceeds, whichever is later; and

                (2) all remaining balances from the proceeds of severance tax bonds issued for a project that has been reauthorized in this act shall revert to the severance tax bonding fund three months after the reversion date for the unexpended balances.

          B. For the purpose of this section, "unexpended balance" means the remainder of an appropriation after reserving for unpaid costs and expenses covered by binding written obligations to third parties.

     SECTION 2. GENERAL FUND AND OTHER FUND APPROPRIATIONS--REVERSIONS.--

          A. Except as otherwise provided in another section of this act:

                (1) the unexpended balance of an appropriation from the general fund or other state fund that has been changed in this act shall revert:

                     (a) at the end of the expenditure period as set forth in this act, if the expenditure period is changed in this act; or

                     (b) if the expenditure period is not changed in this act, pursuant to the time frame set forth in the law in which the original appropriation was made or the time frame set forth in any law that has previously changed the appropriation, whichever is later; and

                (2) all remaining balances of an appropriation from the general fund or other state fund that has been changed in this act shall revert three months after the reversion date for the unexpended balance.

          B. Except as provided in Subsection C of this section, the balance of an appropriation made from the general fund or other state fund shall revert pursuant to Subsection A of this section to the originating fund.

          C. The balance of an appropriation made from the general fund or other state fund to the Indian affairs department or the aging and long-term services department for a project located on lands of an Indian nation, tribe or pueblo shall revert pursuant to Subsection A of this section to the tribal infrastructure project fund.

          D. For the purpose of this section, "unexpended balance" means the remainder of an appropriation after reserving for unpaid costs and expenses covered by binding written obligations to third parties.

     SECTION 3. ATRISCO VISTA BOULEVARD CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 1 of Section 38 of Chapter 81 of Laws 2020 to acquire rights of way for and to plan, design, construct, extend and improve Atrisco Vista boulevard, including bike lanes, in Bernalillo county is extended through fiscal year 2026.

     SECTION 4. BERNALILLO COUNTY SOUTH VALLEY FAMILY SERVICES FACILITY INFORMATION TECHNOLOGY--CHANGE TO FACILITY IMPROVEMENTS--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division originally authorized in Subsection 53 of Section 26 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 8 to plan, design and construct renovations and improvements to the buildings and grounds of a child development and family services facility site in the South Valley in Bernalillo county and to purchase and install teleconferencing and information technology equipment at facility sites in the South Valley and the southeast heights in Albuquerque in Bernalillo county shall not be expended for the original or reauthorized purpose but is changed to plan, design, construct, replace and equip buildings, facilities and grounds at a child development and family services site in the South Valley in Bernalillo county. The time of expenditure is extended through fiscal year 2026.

     SECTION 5. BERNALILLO COUNTY GUTIERREZ-HUBBELL HOUSE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 16 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, equip and furnish site, accessibility and building improvements, including an addition to the main house, at the Gutierrez-Hubbell house open space in the traditional Pajarito village center in Bernalillo county is extended through fiscal year 2026.

     SECTION 6. BERNALILLO COUNTY RIO BRAVO PARK IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 20 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, equip and furnish improvements, including to roads, drainage, trails, soccer fields, parking, bridges and circulation, at Rio Bravo park in Bernalillo county is extended through fiscal year 2026.

     SECTION 7. BERNALILLO COUNTY STREET FOOD EQUIPMENT PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 26 of Section 30 of Chapter 53 of Laws 2022 to purchase, deliver, install and equip commercial equipment for a commissary kitchen for Bernalillo county food entrepreneurs for the street food institute in Bernalillo county is extended through fiscal year 2026.

     SECTION 8. GATEWOOD AVENUE SOUTHWEST IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 4 of Section 38 of Chapter 81 of Laws 2020 to acquire rights of way and to plan, design and construct road and drainage improvements on Gatewood avenue SW from Bridge boulevard to Five Points road in the Atrisco community in Bernalillo county is extended through fiscal year 2026.

     SECTION 9. ISLETA BOULEVARD RIGHTS-OF-WAY ACQUISITION AND IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 6 of Section 38 of Chapter 81 of Laws 2020 to acquire rights of way for and to plan, design, construct and improve Isleta boulevard SW to the south of Rio Bravo boulevard SW in Bernalillo county is extended through fiscal year 2026.

     SECTION 10. QUIET LANE SOUTHWEST ROAD AND DRAIN IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 7 of Section 38 of Chapter 81 of Laws 2020 to acquire rights of way and to plan, design and construct road and storm drainage improvements on Quiet lane SW from Goff boulevard to the end of the road in the Atrisco community and for other road projects in house district 14 in Bernalillo county is extended through fiscal year 2026.

     SECTION 11. KIRTLAND AIR FORCE BASE GROUND WATER MONITORING WELL CONSTRUCTION--EXPAND PURPOSE--EXTEND TIME--SEVERANCE TAX BONDS.--The department of environment project in Subsection 2 of Section 21 of Chapter 138 of Laws 2021 to plan, design and construct a ground water monitoring well for the Albuquerque-Bernalillo county water utility authority to monitor ethylene dibromide contamination in the area of Kirtland air force base in Bernalillo county may include planning, designing and constructing ground water monitoring wells throughout the Albuquerque-Bernalillo county water utility authority service area in Bernalillo county. The time of expenditure is extended through fiscal year 2026.

     SECTION 12. ALBUQUERQUE-BERNALILLO COUNTY WATER UTILITY AUTHORITY GROUND WATER MONITOR WELL CONSTRUCTION--EXPAND PURPOSE--SEVERANCE TAX BONDS.--The department of environment project in Subsection 1 of Section 22 of Chapter 53 of Laws 2022 to plan, design and construct ground water monitoring wells in the area of the Kirtland air force base bulk fuel facility site for the Albuquerque-Bernalillo county water utility authority in Bernalillo county may include planning, designing and constructing ground water monitoring wells throughout the Albuquerque-Bernalillo county water utility authority service area in Bernalillo county.

     SECTION 13. ALBUQUERQUE SIGN LANGUAGE ACADEMY BUS PURCHASE--CHANGE TO PORTABLE GARAGE--EXTEND TIME--GENERAL FUND.--The unexpended balance of the appropriation to the public education department in Subsection 4 of Section 16 of Chapter 199 of Laws 2023 to purchase and equip activity buses, including wheelchair lifts, for the Albuquerque sign language academy charter school in Bernalillo county shall not be expended for the original purpose but is changed to purchase a portable building for use as a garage at the Albuquerque sign language academy charter school. The time of expenditure is extended through fiscal year 2026.

     SECTION 14. ALBUQUERQUE ADELANTE DEVELOPMENT CENTER EQUIPMENT AND VEHICLE PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 34 of Section 30 of Chapter 53 of Laws 2022 to purchase and equip vehicles, furniture and equipment, including information technology, sanitation equipment and warehouse equipment, for an organization providing residential and adult daycare services and employment training and assistance for disadvantaged populations in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 15. ALBUQUERQUE AFFORDABLE HOUSING CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 37 of Section 35 of Chapter 81 of Laws 2020 to acquire land for and to plan, design and construct affordable housing and homeless facilities in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 16. ALBUQUERQUE ALL FAITHS VEHICLE AND EQUIPMENT PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 39 of Section 30 of Chapter 53 of Laws 2022 to purchase and equip vehicles and to purchase and install equipment and furnishings, including coronavirus-disease-2019-safe office furniture, playground equipment and information technology, including equipment and infrastructure, at a facility promoting the healing of children in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 17. ALBUQUERQUE BUSINESS INCUBATOR AND KITCHEN CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 46 of Section 35 of Chapter 81 of Laws 2020 to acquire property and to plan, design, construct, demolish, renovate, improve, equip, furnish and install equipment for a food business incubator and kitchen in the downtown area of Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 18. ALBUQUERQUE OPEN SPACE, PARKS AND TRAILS CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the local government division project originally authorized in Subsection 43 of Section 34 of Chapter 277 of Laws 2019 and reauthorized in Laws 2022, Chapter 52, Section 18 to acquire property for and to plan, design, construct and equip the Crestview bluff open space area, parks and trails in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 19. ALBUQUERQUE DISTRICT SIX ART CORRIDOR SAFETY IMPROVEMENT--EXTEND TIME--GENERAL FUND.--The time of expenditure for the department of transportation project in Subsection 10 of Section 75 of Chapter 81 of Laws 2020 to plan, design, construct and improve pedestrian safety and access to businesses along the Albuquerque rapid transit corridor in city council district 6 in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 20. ALBUQUERQUE DISTRICT SIX STREET LIGHTING IMPROVEMENT--EXTEND TIME--GENERAL FUND.--The time of expenditure for the department of transportation project in Subsection 11 of Section 75 of Chapter 81 of Laws 2020 to plan, design, construct, purchase and install improvements and additions to street lighting in city council district 6 in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 21. ALBUQUERQUE DISTRICT FIVE MEDIAN IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 9 of Section 38 of Chapter 81 of Laws 2020 to plan, design, construct, purchase and install irrigation and landscaping of medians in city council district 5 in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 22. ALBUQUERQUE WEST SIDE INDOOR SPORTS FACILITY CONSTRUCTION--CHANGE TO INDOOR SPORTS COMPLEX--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division in Subsection 108 of Section 29 of Chapter 138 of Laws 2021 to plan, design, construct, furnish and equip a west side indoor sports facility in Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to acquire land for and to plan, design, construct, improve, furnish and equip an indoor sports complex near the Jennifer Riordan spark kindness sports complex in Albuquerque in Bernalillo county. The time of expenditure is extended through fiscal year 2026.

     SECTION 23. ALBUQUERQUE WEST SIDE SPORTS COMPLEX CONSTRUCTION--CHANGE TO INDOOR SPORTS COMPLEX--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division originally authorized in Subsection 121 of Section 34 of Chapter 277 of Laws 2019 and reauthorized in Laws 2023, Chapter 203, Section 31 to acquire land and rights of way for and to plan, design, construct, furnish and equip an indoor sports complex in the west side area of Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to acquire land for and to plan, design, construct, improve, furnish and equip an indoor sports complex near the Jennifer Riordan spark kindness sports complex in Albuquerque in Bernalillo county. The time of expenditure is extended through fiscal year 2026.

     SECTION 24. ALBUQUERQUE WEST SIDE INDOOR RECREATION COMPLEX CONSTRUCTION--CHANGE TO INDOOR SPORTS COMPLEX IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division in Subsection 141 of Section 30 of Chapter 53 of Laws 2022 to acquire land and to plan, design, construct, improve and equip an indoor recreation complex on the west side of Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to acquire land for and to plan, design, construct, improve, furnish and equip an indoor sports complex near the Jennifer Riordan spark kindness sports complex in Albuquerque in Bernalillo county. The time of expenditure is extended through fiscal year 2026.

     SECTION 25. JOAN JONES COMMUNITY CENTER IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project originally authorized in Subsection 36 of Section 26 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 24 to plan, design, construct, expand, equip and furnish phase 2 improvements to the Joan Jones community center in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 26. KIRTLAND PARK MURAL REPAIR--CHANGE TO KIRTLAND PARK RENOVATION--GENERAL FUND.--The unexpended balance of the appropriation to the local government division in Subsection 79 of Section 28 of Chapter 199 of Laws 2023 to plan, design, construct, repair and restore a mural on the grounds of Kirtland park and the Thomas Bell community center in Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to plan, design, construct, renovate and equip Kirtland park in Albuquerque in Bernalillo county.

     SECTION 27. ALBUQUERQUE CRESTVIEW BLUFF OPEN SPACE AREA CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the local government division project originally authorized in Subsection 5 of Section 34 of Chapter 277 of Laws 2019 and reauthorized in Laws 2022, Chapter 52, Section 17 to acquire property for and to plan, design, construct and equip the Crestview bluff open space area, parks and trails in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 28. SAN JOSE NEIGHBORHOOD SOUND WALL CONSTRUCTION--CHANGE TO SOUTH SAN JOSE PARK RENOVATION--CHANGE AGENCY--GENERAL FUND.--The unexpended balance of the appropriation to the department of transportation in Subsection 26 of Section 33 of Chapter 199 of Laws 2023 to plan, design and construct a sound wall in the San Jose neighborhood in Albuquerque in Bernalillo county shall not be expended for the original purpose but is appropriated to the local government division to plan, design, construct, renovate, expand and equip south San Jose park in Albuquerque in Bernalillo county.

     SECTION 29. ALBUQUERQUE SAN JOSE NEIGHBORHOOD SOUND WALL CONSTRUCTION--CHANGE TO SOUTH SAN JOSE PARK RENOVATION--CHANGE AGENCY--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the department of transportation in Subsection 18 of Section 33 of Chapter 138 of Laws 2021 to plan, design and construct a sound wall in the San Jose neighborhood in Albuquerque in Bernalillo county shall not be expended for the original purpose but is appropriated to the local government division to plan, design, construct, renovate, equip and expand south San Jose park in Albuquerque in Bernalillo county. The time of expenditure is extended through fiscal year 2026.

     SECTION 30. ALBUQUERQUE PROTON BEAM CANCER TREATMENT FACILITY CONSTRUCTION--CHANGE TO SURGICAL CENTER--GENERAL FUND.--The unexpended balance of the local government division project in Subsection 106 of Section 28 of Chapter 199 of Laws 2023 to plan, design, construct, furnish and equip a proton beam cancer treatment facility in Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to plan, design, construct, acquire, furnish and equip a surgical center for a clinically integrated health care network in Albuquerque in Bernalillo county.

     SECTION 31. ALBUQUERQUE TAYLOR RANCH LIBRARY IMPROVEMENT AND COMMUNITY ROOM CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 118 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, expand and make improvements, including a community room, to the Taylor Ranch library in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 32. UNSER MUSEUM CONSTRUCTION--CHANGE TO CONSTRUCT A WEST SIDE SPRAY PAD--GENERAL FUND.--The unexpended balance of the appropriation to the local government division in Subsection 133 of Section 28 of Chapter 199 of Laws 2023 to plan, design, construct, furnish and equip the Unser museum in the area of Central avenue and Unser boulevard in Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to plan, design, construct and equip a spray pad on the west side in Albuquerque in Bernalillo county.

     SECTION 33. ALBUQUERQUE WEST SIDE SPORTS COMPLEX CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 124 of Section 35 of Chapter 81 of Laws 2020 to acquire land and to plan, design, construct, furnish and equip an indoor sports complex near the Jennifer Riordan spark kindness sports complex in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 34. ALBUQUERQUE YOUTH TEMPORARY HOUSING FACILITY CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 126 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, purchase and equip a facility to provide temporary housing for youth in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 35. ATRISCO LAND GRANT MONUMENT AND MEMORIAL PARK CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 9 of Section 35 of Chapter 81 of Laws 2020 to acquire land and to plan, design and construct an Atrisco land grant monument and memorial plaza park in the Atrisco community in Bernalillo county is extended through fiscal year 2026.

     SECTION 36. ALBUQUERQUE SPORTS AND CULTURAL CENTER CONSTRUCTION--CHANGE TO BALLOON FIESTA PARK IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the local government division project in Subsection 116 of Section 35 of Chapter 81 of Laws 2020 to acquire land for and to plan, design and construct phase 1 of a sports and cultural center, including art exhibits, public outdoor spaces, retail and dining facilities and playing fields, in Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to acquire land for and to plan, design and construct infrastructure for a multi-use facility, including public outdoor spaces and playing fields, at Balloon Fiesta park in Albuquerque in Bernalillo county. The time of expenditure is extended through fiscal year 2026.

     SECTION 37. BARELAS LIVE/WORK INCUBATOR FOR CREATIVES--CHANGE TO BARELAS METROPOLITAN REDEVELOPMENT AREA IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division in Subsection 130 of Section 35 of Chapter 81 of Laws 2020 to plan, design, renovate and construct a building for a live/work incubator for creative entrepreneurs in the Barelas metropolitan redevelopment area in Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to plan, design, construct and improve the Barelas metropolitan redevelopment area in Albuquerque in Bernalillo county. The time of expenditure is extended through fiscal year 2026.

     SECTION 38. BERNALILLO COUNTY METROPOLITAN COURT ELEVATOR GRIPPER INSTALLATION--CHANGE TO INFRASTRUCTURE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the Bernalillo county metropolitan court in Subsection 1 of Section 6 of Chapter 53 of Laws 2022 to plan, design, purchase, equip and install linear rope grippers to secure elevators at the Bernalillo county metropolitan court in Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to plan, design, construct, purchase, repair and improve court facilities, including heating, ventilation and air conditioning systems, structural and drainage improvements, security access control panels and fire suppression systems, at the Bernalillo county metropolitan court. The time of expenditure is extended through fiscal year 2026.

     SECTION 39. BERNALILLO COUNTY METROPOLITAN COURT LAND ACQUISITION AND SITE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Bernalillo county metropolitan court project in Subsection 1 of Section 6 of Chapter 81 of Laws 2020 to acquire property adjacent to the existing court facilities and for design, engineering, demolition, construction and equipment to improve security and access for the Bernalillo county metropolitan court in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 40. BERNALILLO COUNTY METROPOLITAN COURT PARKING SYSTEM AND SECURITY IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Bernalillo county metropolitan court project in Laws 2021, Chapter 138, Section 6 to plan, design, purchase, equip and install improvements, including a parking operating system and a courtroom security system, at the Bernalillo county metropolitan court in Bernalillo county is extended through fiscal year 2026.

     SECTION 41. BERNALILLO COUNTY SPLASH PARK CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 131 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, equip and furnish a new splash park in Bernalillo county is extended through fiscal year 2026.

     SECTION 42. BERNALILLO COUNTY TRANSITIONAL LIVING AND RECOVERY CENTER CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 28 of Section 35 of Chapter 81 of Laws 2020 to acquire land and buildings and to plan, design, construct, demolish and renovate new and existing buildings, parking lots, landscaping, utilities, fencing, roofs and water suppression systems facilities for a transitional living and substance abuse recovery center for adolescents and young adults in Bernalillo county is extended through fiscal year 2026.

     SECTION 43. GREENWICH ROAD SOUTHWEST IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 5 of Section 38 of Chapter 81 of Laws 2020 to acquire rights of way and to plan, design and construct road and storm drainage improvements on Greenwich road SW from the cul-de-sac at the end of the road north to the sharp bend west of La Vega drive in the Atrisco community and for other road projects in house district 14 in Bernalillo county is extended through fiscal year 2026.

     SECTION 44. INDIAN PUEBLO CULTURAL CENTER EARLY CHILDHOOD DEVELOPMENT CENTER CONSTRUCTION--CHANGE TO FACILITY EXPANSION--GENERAL FUND.--The unexpended balance of the appropriation to the Indian affairs department in Subsection 2 of Section 25 of Chapter 199 of Laws 2023 to plan, design, construct, furnish and equip an early childhood development center at the Indian Pueblo cultural center in Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to acquire land for and to plan, design, construct and expand facilities at the Indian Pueblo cultural center.

     SECTION 45. MCMAHON BOULEVARD IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 11 of Section 38 of Chapter 81 of Laws 2020 to acquire rights of way and to plan, design and construct road, signal and safety improvements to McMahon boulevard from Rockcliff drive to Anasazi Ridge avenue and Kayenta street in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 46. PASEO DEL NORTE NORTHWEST IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 12 of Section 38 of Chapter 81 of Laws 2020 to acquire rights of way on paseo del Norte NW between Rainbow boulevard to calle Nortena and to plan, design and construct improvements on paseo del Norte NW from Kimmick drive to Unser boulevard in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 47. INDIGENOUS DESIGN AND PLANNING INSTITUTE INFORMATION TECHNOLOGY IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the university of New Mexico project in Subsection 8 of Section 43 of Chapter 53 of Laws 2022 to purchase and install upgrades to information technology, including related equipment, furniture and infrastructure, for the indigenous design and planning institute at the university of New Mexico in Albuquerque in Bernalillo county is extended through fiscal year 2026.

     SECTION 48. WILDWOOD LANE SOUTHWEST IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 8 of Section 38 of Chapter 81 of Laws 2020 to acquire rights of way and to plan, design and construct road and drainage improvements on Wildwood lane SW from Goff boulevard to the end of the lane in the Atrisco community and for other road projects in house district 14 in Bernalillo county is extended through fiscal year 2026.

     SECTION 49. ALBUQUERQUE PUBLIC SCHOOL DISTRICT CROSSWALK IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 13 of Section 38 of Chapter 81 of Laws 2020 to plan, design, construct, expand and improve crosswalks for schools in the Albuquerque public school district in Bernalillo county is extended through fiscal year 2026.

     SECTION 50. TIJERAS COMMUNITY WATER WELL CONSTRUCTION--CHANGE TO WATER SYSTEM IMPROVEMENT--GENERAL FUND.--The unexpended balance of the appropriation to the department of environment in Subsection 11 of Section 19 of Chapter 199 of Laws 2023 to plan, design and construct a water well for the Tijeras community water system in Tijeras in Bernalillo county shall not be expended for the original purpose but is changed to plan, design, construct, purchase and install water system improvements, including meters and remote monitoring equipment, in Tijeras in Bernalillo county.

     SECTION 51. TIJERAS WELL CONSTRUCTION--EXPAND PURPOSE--EXTEND TIME--SEVERANCE TAX BONDS.--The department of environment project in Subsection 5 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct a third well and related infrastructure in Tijeras in Bernalillo county may include planning, designing and constructing a storage tank. The time of expenditure is extended through fiscal year 2026.

     SECTION 52. CHAVES COUNTY INDUSTRIAL SITE UTILITY AND INFRASTRUCTURE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 150 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, purchase, install and expand utilities and infrastructure, including water towers, power poles, utility lines, roads, sidewalks and pavement, at the Roswell industrial air center in Chaves county is extended through fiscal year 2026.

     SECTION 53. LAKE ARTHUR TOWN HALL ROOF REPLACEMENT--EXPAND PURPOSE--EXTEND TIME--SEVERANCE TAX BONDS.--The local government division project in Subsection 160 of Section 30 of Chapter 53 of Laws 2022 to design, construct and replace a roof for an administrative building in Lake Arthur in Chaves county may include the purchase and installation of fencing, site work, infrastructure improvements and relocation of a portable building in Lake Arthur. The time of expenditure is extended through fiscal year 2026.

     SECTION 54. SAN RAFAEL WATER AND SANITATION DISTRICT WATER METER PURCHASE--CHANGE TO HEAVY EQUIPMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the department of environment in Subsection 13 of Section 22 of Chapter 53 of Laws 2022 to purchase, install and replace water meters, including related information technology, equipment and infrastructure, in the San Rafael water and sanitation district in Cibola county shall not be expended for the original purpose but is changed to purchase and equip heavy equipment and machinery for the San Rafael water and sanitation district. The time of expenditure is extended through fiscal year 2026.

     SECTION 55. ACOMA PUEBLO BUSINESS DEVELOPMENT FACILITY CONSTRUCTION--CHANGE TO BROADBAND NETWORK OPERATIONS CENTER--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the Indian affairs department in Subsection 6 of Section 25 of Chapter 138 of Laws 2021 to plan, design, construct, furnish and equip small business development facilities for the Pueblo of Acoma in Cibola county shall not be expended for the original purpose but is changed to plan, design, construct, furnish and equip a community broadband network operations center for the Pueblo of Acoma in Cibola county. The time of expenditure is extended through fiscal year 2026.

     SECTION 56. RAMAH CHAPTER EMERGENCY MEDICAL SERVICES SUBSTATION CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 10 of Section 70 of Chapter 81 of Laws 2020 to plan, design, construct, furnish and equip an emergency medical services substation for the Ramah chapter of the Navajo Nation in Cibola county is extended through fiscal year 2026.

     SECTION 57. NORTHWEST NEW MEXICO COUNCIL OF GOVERNMENTS BUILDING IMPROVEMENT--CHANGE TO RAMAH CHAPTER COMMUNITY CENTER CONSTRUCTION--CHANGE AGENCY--SEVERANCE TAX BONDS.--Up to thirty-three percent of the unexpended balance of the appropriation to the local government division in Subsection 296 of Section 30 of Chapter 53 of Laws 2022 to plan, design, construct and improve the northwest New Mexico council of governments building in Gallup in McKinley county shall not be expended for the original purpose but is appropriated to the Indian affairs department to plan, design, construct, furnish and equip a community center for the Ramah chapter of the Navajo Nation in Cibola county.

     SECTION 58. RAMAH CHAPTER SOLID WASTE TRANSFER STATION CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 6 of Section 20 of Chapter 81 of Laws 2016 and reauthorized in Laws 2020, Chapter 82, Section 32 and again reauthorized in Laws 2022, Chapter 52, Section 43 to plan, design and construct a solid waste transfer station, including a trash compactor dumpster, a trash bin and an operator building, in the Ramah chapter of the Navajo Nation in Cibola county is extended through fiscal year 2026.

     SECTION 59. RAMAH CHAPTER SOLID WASTE TRANSFER STATION CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 6 of Section 22 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 77 to plan, design, purchase, construct, equip and install a solid waste transfer station, including a trash compactor dumpster, a trash bin and an operator building, in the Ramah chapter of the Navajo Nation in Cibola county is extended through fiscal year 2026.

     SECTION 60. ANGEL FIRE VIETNAM VETERANS MEMORIAL IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the veterans' services department project originally authorized in Laws 2020, Chapter 81, Section 47 to plan, design, construct, repair, furnish, equip and make site improvements, including a memorial wall, at the Vietnam veterans memorial in Angel Fire in Colfax county and reauthorized to the capital program fund in Laws 2022, Chapter 52, Section 128 for that purpose is extended through fiscal year 2026.

     SECTION 61. TEXICO WATER TANK IMPROVEMENT--CHANGE TO CURRY COUNTY FAIRGROUND IMPROVEMENT--CHANGE AGENCY--EXTEND TIME--GENERAL FUND.--The unexpended balance of the appropriation to the department of environment originally authorized in Subsection 17 of Section 26 of Chapter 277 of Laws 2019 and reauthorized in Laws 2023, Chapter 203, Section 87 to plan, design, repair and rehabilitate water tanks in Texico in Curry county shall not be expended for the original or reauthorized purpose but is appropriated to the local government division to plan, design, construct and improve the fairgrounds, including fencing, lighting, parking and buildings, in Curry county. The time of expenditure is extended through fiscal year 2026.

     SECTION 62. TEXICO WATER SYSTEM IMPROVEMENT--CHANGE TO CURRY COUNTY FAIRGROUND IMPROVEMENTS--CHANGE AGENCY--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the department of environment originally authorized in Subsection 56 of Section 26 of Chapter 81 of Laws 2020 and reauthorized in Laws 2022, Chapter 52, Section 49 to plan, design, construct and improve contaminated water systems in Texico in Curry county shall not be expended for the original or reauthorized purpose but is appropriated to the local government division to plan, design, construct and improve the fairgrounds, including fencing, lighting, parking and buildings, in Curry county. The time of expenditure is extended through fiscal year 2026.

     SECTION 63. CURRY COUNTY JUDICIAL CENTER MAGISTRATE COURT PLAN--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the administrative office of the courts project in Subsection 1 of Section 4 of Chapter 81 of Laws 2020 to plan, design and construct a magistrate court judicial center in Curry county is extended through fiscal year 2026.

     SECTION 64. DESERT AIRE WASTEWATER SYSTEM IMPROVEMENTS--CHANGE TO ANTHONY WATER AND SANITATION DISTRICT VEHICLE PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the department of environment in Subsection 18 of Section 26 of Chapter 81 of Laws 2020 to acquire easements, rights of way and land and to plan, design, construct, purchase and equip wastewater system improvements for the community of Desert Aire in Dona Ana county shall not be expended for the original purpose but is changed to purchase and equip vehicles for the Anthony water and sanitation district in Dona Ana county. The time of expenditure is extended through fiscal year 2026.

     SECTION 65. THIRD JUDICIAL DISTRICT COURT CONSTRUCTION--CHANGE AGENCY--GENERAL FUND.--The unexpended balance of the appropriation to the third judicial district court in Laws 2023, Chapter 199, Section 13 to plan, design, construct and equip an addition to the third judicial district court facility in Dona Ana county is appropriated to the local government division for that purpose.

     SECTION 66. SPRING CANYON ARROYO DAM CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the office of the state engineer project originally authorized in Subsection 5 of Section 25 of Chapter 81 of Laws 2020 and reauthorized in Laws 2021, Chapter 139, Section 24 to plan, design, acquire property for, construct and equip a flood control dam on the lower Spring canyon arroyo in Dona Ana county is extended through fiscal year 2026.

     SECTION 67. VISTA DEL REY ESTATES MUTUAL DOMESTIC WATER CONSUMERS ASSOCIATION WATER SYSTEM IMPROVEMENT--CHANGE TO IMPROVE VISTA DEL REY ROAD--CHANGE AGENCY--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the department of environment in Subsection 22 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct water system improvements, including booster station and water line improvements and interconnection with the High Valley Estates water system, for the Vista del Rey Estates mutual domestic water consumers association in Dona Ana county shall not be expended for the original purpose but is appropriated to the department of transportation to plan, design, construct and improve Vista del Rey road, including protective measures for water lines, in Dona Ana county. The time of expenditure for the project is extended through fiscal year 2026.

     SECTION 68. DONA ANA COUNTY REPRODUCTIVE HEALTH CARE CLINIC CONSTRUCTION--CHANGE TO UNIVERSITY OF NEW MEXICO DONA ANA COUNTY CLINIC--CHANGE AGENCY--GENERAL FUND.--The unexpended balance of the appropriation to the local government division in Subsection 1 of Section 21 of Chapter 199 of Laws 2023 to plan, design and construct a reproductive health care clinic in Dona Ana county shall not be expended for the original purpose but is appropriated to the board of regents of the university of New Mexico to plan, design, acquire, construct, improve, furnish and equip a reproductive health care clinic for the university of New Mexico in Dona Ana county.

     SECTION 69. DONA ANA COUNTY MAGISTRATE COURT PLAN--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the administrative office of the courts project in Subsection 2 of Section 4 of Chapter 81 of Laws 2020 to plan, design and construct a magistrate court building in Anthony in Dona Ana county is extended through fiscal year 2026.

     SECTION 70. GARFIELD MUTUAL DOMESTIC WATER CONSUMERS AND MUTUAL SEWAGE WORKS ASSOCIATION WATER SUPPLY WELL DESIGN--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 63 of Section 22 of Chapter 53 of Laws 2022 to plan, design and permit a fluoride water treatment system for the Garfield mutual domestic water consumers and mutual sewage works association in Sierra and Dona Ana counties is extended through fiscal year 2026.

     SECTION 71. DONA ANA COUNTY MULTIPURPOSE TRAIL CONNECTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 192 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, equip and install a multipurpose trail to connect Mesilla with the Las Cruces trail system in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 72. DONA ANA COUNTY TORTUGAS TRAIL CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 204 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, furnish and equip a multipurpose trail with the Tortugas trail development in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 73. LAS CRUCES AMADOR HOTEL IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project originally authorized in Subsection 203 of Section 34 of Chapter 277 of Laws 2019 to plan, design, construct and equip a parking garage in Las Cruces in Dona Ana county and reauthorized in Laws 2022, Chapter 52, Section 52 to plan, design, construct, furnish, equip and install improvements, including related infrastructure, to the Amador hotel in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 74. LAS CRUCES ARTS AND CULTURAL DISTRICT IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 207 of Section 35 of Chapter 81 of Laws 2020 to acquire rights of way and to plan, design, construct, improve, expand, purchase, equip and install way-finding and lighting systems, the restoration of two parks and a community garden, shade structures, bandstands and gateways in Klein park and the arts and cultural district in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 75. EAST MESA AVENUE IMPROVEMENT--CHANGE TO EAST MESA AREA ROADS--GENERAL FUND.--The unexpended balance of the appropriation to the department of transportation in Subsection 55 of Section 33 of Chapter 199 of Laws 2023 to acquire rights of way and to plan, design, construct and improve east Mesa avenue, including pavement replacement, curb and gutter, sidewalks, accessibility and code compliance, drainage, lighting, signage, striping and related infrastructure and utilities, in Las Cruces in Dona Ana county shall not be expended for the original purpose but is changed to acquire rights of way for and to plan, design, construct and improve roads in the east Mesa area, including pavement replacement, curb and gutter, sidewalks, accessibility and code compliance, drainage, lighting, signage, striping and related infrastructure and utilities, in Las Cruces in Dona Ana county.

     SECTION 76. LAS CRUCES EAST SIDE ROAD AND DRAIN CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 14 of Section 38 of Chapter 81 of Laws 2020 to acquire rights of way and to plan, design and construct roads, including curb and gutter, utilities and flood control, on the east side of Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 77. LAS CRUCES INTERNATIONAL AIRPORT RUNWAY EXTENSION--CHANGE TO INFRASTRUCTURE IMPROVEMENT--CHANGE AGENCY--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the department of transportation project in Subsection 23 of Section 38 of Chapter 81 of Laws 2020 to plan, design and construct an extension to runway 12/30 at the Las Cruces international airport in Las Cruces in Dona Ana county shall not be expended for the original purpose but is appropriated to the local government division to plan, design, construct, renovate, purchase, furnish and equip infrastructure improvements, including utilities, for the Las Cruces international airport. The time of expenditure is extended through fiscal year 2026.

     SECTION 78. LAS CRUCES INTERNATIONAL AIRPORT IMPROVEMENT--EXTEND TIME--GENERAL FUND.--The time of expenditure for the local government division project originally authorized in Subsection 203 of Section 34 of Chapter 277 of Laws 2019 and reauthorized in Laws 2022, Chapter 52, Section 56 to plan, design, construct, furnish, equip and install improvements, including related infrastructure and landscaping, to the Las Cruces international airport in Dona Ana county is extended through fiscal year 2026.

     SECTION 79. LAS CRUCES PIONEER WOMEN'S PARK IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 213 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, purchase, equip and install improvements at Pioneer Women's park in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 80. LAS CRUCES SEPTIC TANK REPLACEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 24 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct a septic replacement project in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 81. LAS CRUCES SKATE PARK CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 218 of Section 35 of Chapter 81 of Laws 2020 to acquire land, rights of way and easements and to plan, design, construct, equip, purchase and install a new skate park in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 82. LAS CRUCES SKATE PARK RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 219 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate and equip the skate park in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 83. LAS CRUCES SOCCER COMPLEX IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 220 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, purchase, equip and install renovations at the High Noon soccer complex in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 84. MESILLA VALLEY COMMUNITY OF HOPE HEALTH FACILITY--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 210 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, furnish and equip a health facility for Mesilla Valley community of hope in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 85. NEW MEXICO STATE UNIVERSITY WOMEN'S SOCCER FIELD TURF REPLACEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the New Mexico state university project in Subsection 13 of Section 41 of Chapter 53 of Laws 2022 to design and replace the women's soccer field at New Mexico state university in Las Cruces in Dona Ana county is extended through fiscal year 2026.

     SECTION 86. SOUTH CENTRAL REGIONAL TRANSIT DISTRICT MIDSIZED TRANSIT BUS PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 210 of Section 30 of Chapter 53 of Laws 2022 to match federal funding to purchase, equip and replace buses for the south central regional transit district in Dona Ana county is extended through fiscal year 2026.

     SECTION 87. EDDY COUNTY INFORMATION TECHNOLOGY PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 237 of Section 30 of Chapter 53 of Laws 2022 to upgrade information technology systems, including equipment and infrastructure, for the 911 center in Artesia and to purchase and equip an off-site backup system and monitoring hardware in Eddy county is extended through fiscal year 2026.

     SECTION 88. NATIONAL PARKS HIGHWAY SEWER LINE CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 26 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct a sewer line, including a sewer interceptor, manholes, fittings and attachments, along National Parks highway in Carlsbad in Eddy county is extended through fiscal year 2026.

     SECTION 89. RADIO BOULEVARD CARLSBAD IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 15 of Section 38 of Chapter 81 of Laws 2020 to plan, design and construct improvements to Radio boulevard, including curb and gutter, in Carlsbad in Eddy county is extended through fiscal year 2026.

     SECTION 90. LOVING SEWER COLLECTION AND WASTEWATER TREATMENT PLANT IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 28 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct improvements to sewer collection and a wastewater treatment plant, including replacement of sewer mains, replacement and installation of manholes, service reconnection and the installation of security fencing and gates, in Loving in Eddy county is extended through fiscal year 2026.

     SECTION 91. CASAS ADOBES MUTUAL DOMESTIC WATER CONSUMERS ASSOCIATION BACKHOE PURCHASE--EXPAND PURPOSE--EXTEND TIME--GENERAL FUND.--The department of environment project in Subsection 49 of Section 19 of Chapter 199 of Laws 2023 to purchase and equip a backhoe for the Casas Adobes mutual domestic water consumers association in Grant county may include planning, designing and constructing water system improvements and the purchase and installation of a supervisory control and data acquisition system for that association. The time of expenditure is extended through fiscal year 2026.

     SECTION 92. ACEQUIA DE VADO DE JUAN PAIZ EROSION CONTROL IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 7 of Section 34 of Chapter 81 of Laws 2020 to purchase and install erosion control devices and to plan, design and construct infrastructure improvements for the acequia de Vado de Juan Paiz in Guadalupe county is extended through fiscal year 2026.

     SECTION 93. NOR-LEA SPECIAL HOSPITAL DISTRICT EMERGENCY ROOM BEHAVIORAL HEALTH RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 254 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, expand and furnish the emergency room to improve privacy and service to behavioral health patients in the Nor-Lea special hospital district in Lea county is extended through fiscal year 2026.

     SECTION 94. EUNICE RODEO ARENA CONSTRUCTION--CHANGE PURPOSE--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division originally authorized in Subsection 220 of Section 29 of Chapter 138 of Laws 2021 and reauthorized in Laws 2022, Chapter 52, Section 62 to plan, design, construct and equip a youth sports complex, including baseball, softball, football and soccer fields, for Eunice in Lea county shall not be expended for the original or reauthorized purpose but is changed to plan, design, construct and furnish a covered rodeo arena, including a recreational vehicle park, landscaping, lighting, sidewalks, parking and fencing, in Eunice in Lea county. The time of expenditure is extended through fiscal year 2026.

     SECTION 95. EUNICE RODEO ARENA CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 248 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct and furnish a covered rodeo arena, including a recreational vehicle park, landscaping, lighting, sidewalks, parking and fencing, in Eunice in Lea county is extended through fiscal year 2026.

     SECTION 96. NEW MEXICO JUNIOR COLLEGE HAGELSTEIN INSTRUCTIONAL ARTS CENTER CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the higher education department project originally authorized in Subsection 5 of Section 39 of Chapter 81 of Laws 2020 and reauthorized in Laws 2023, Chapter 203, Section 114 to plan, design, construct, renovate, repair and equip the Mary Hagelstein instructional arts center at New Mexico junior college in Lea county is extended through fiscal year 2026.

     SECTION 97. NEW MEXICO JUNIOR COLLEGE VOCATIONAL TECHNICAL EQUIPMENT PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the higher education department project in Subsection 7 of Section 37 of Chapter 53 of Laws 2022 to purchase and equip portable teaching welding laboratories at New Mexico junior college in Lea county is extended through fiscal year 2026.

     SECTION 98. JAL WATER STORAGE TANKS IMPROVEMENT--EXTEND TIME--GENERAL FUND.--The time of expenditure for the department of environment project in Subsection 5 of Section 66 of Chapter 81 of Laws 2020 to plan, design, purchase, construct and equip improvements to water storage tanks in Jal in Lea county is extended through fiscal year 2026.

     SECTION 99. LEA COUNTY HISTORIC COURTHOUSE RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 251 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, purchase, equip and furnish renovations to the historic county courthouse in Lovington in Lea county is extended through fiscal year 2026.

     SECTION 100. LOVINGTON LEA THEATRE IMPROVEMENTS--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 252 of Section 35 of Chapter 81 of Laws 2020 to plan, design, purchase, construct and equip improvements to the historic Lea theatre in Lovington in Lea county is extended through fiscal year 2026.

     SECTION 101. LOVINGTON VETERANS' MEMORIAL CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 253 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, purchase and equip a veterans' memorial and park in Lovington in Lea county is extended through fiscal year 2026.

     SECTION 102. LOVINGTON WATER DEPARTMENT OFFICE BUILDING RENOVATION--EXPAND PURPOSE--SEVERANCE TAX BONDS.--The local government division project in Subsection 269 of Section 30 of Chapter 53 of Laws 2022 to plan, design, construct and equip an addition to the water department office building in Lovington in Lea county may include design, construction, purchase, installation and improvement of heating, ventilation and air conditioning systems in the building.

     SECTION 103. LOVINGTON WELL CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project originally authorized in Subsection 19 of Section 11 of Chapter 64 of Laws 2012 to plan, design and construct wells in Lovington in Lea county and reauthorized in Laws 2016, Chapter 83, Section 52 and again in Laws 2018, Chapter 68, Section 66 to include the purchase and installation of equipment for water wells and water system improvements in Lovington and again in Laws 2020, Chapter 82, Section 46 and again in Laws 2022, Chapter 52, Section 64 is extended through fiscal year 2026.

     SECTION 104. CARRIZOZO WATER SYSTEM IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 38 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct water system improvements in Carrizozo in Lincoln county is extended through fiscal year 2026.

     SECTION 105. COLUMBUS PORT OF ENTRY FLOOD CONTROL INFRASTRUCTURE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the border authority project in Laws 2020, Chapter 81, Section 7 to plan, design, construct and make infrastructure improvements for flood and erosion control at the Columbus port of entry in Luna county is extended through fiscal year 2026.

     SECTION 106. COLUMBUS VEHICLE PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 284 of Section 30 of Chapter 53 of Laws 2022 to purchase and equip a waste refuse transfer truck for Columbus in Luna county is extended through fiscal year 2026.

     SECTION 107. MCKINLEY COUNTY BRIDGES CONSTRUCTION--CHANGE TO ROAD CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the department of transportation in Subsection 65 of Section 36 of Chapter 53 of Laws 2022 to plan, design, construct, improve, repair and replace bridges in McKinley county shall not be expended for the original purpose but is changed to plan, design and construct roads in the Baahaali chapter of the Navajo Nation in McKinley county. The time of expenditure is extended through fiscal year 2026.

     SECTION 108. UNIVERSITY OF NEW MEXICO-GALLUP CALVIN HALL REPAIR--CHANGE TO BAAHAALI CHAPTER HOUSE IMPROVEMENT--CHANGE AGENCY--GENERAL FUND.--The unexpended balance of the appropriation to the university of New Mexico-Gallup in Subsection 31 of Section 40 of Chapter 199 of Laws 2023 to plan, design, construct, purchase and repair the exterior of Calvin hall, including stucco repairs, at the Gallup branch campus of the university of New Mexico in McKinley county shall not be expended for the original purpose but is appropriated to the Indian affairs department to plan, design, construct and equip improvements to the chapter house heating, ventilation and air conditioning systems in the Baahaali chapter of the Navajo Nation in McKinley county.

     SECTION 109. BACA/PREWITT CHAPTER POWER LINE EXTENSION--CHANGE TO NAVAJO ROUTE 30 AND UNITED STATES HIGHWAY 491 LIGHTING--CHANGE AGENCY--EXTEND TIME--GENERAL FUND.--The unexpended balance of the appropriation to the Indian affairs department in Subsection 13 of Section 70 of Chapter 81 of Laws 2020 to acquire rights of way, to perform archaeological and environmental studies and to plan, design and construct a power line extension for the Baca/Prewitt chapter of the Navajo Nation in McKinley county shall not be expended for the original purpose but is appropriated to the department of transportation to plan, design, construct and equip lighting at the junction of Navajo route 30 and United States highway 491 in the Mexican Springs chapter of the Navajo Nation in McKinley county. The time of expenditure is extended through fiscal year 2026.

     SECTION 110. BAAHAALI CHAPTER SEWAGE LAGOON IMPROVEMENT--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 12 of Section 70 of Chapter 81 of Laws 2020 to plan, design, construct and equip improvements to the sewage lagoon for the Baahaali chapter of the Navajo Nation in McKinley county is extended through fiscal year 2026.

     SECTION 111. BAAHAALI/CHICHILTAH REGIONAL TRANSFER STATION IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project originally authorized in Subsection 46 of Section 26 of Chapter 81 of Laws 2020 and appropriated to the Indian affairs department in Laws 2021, Chapter 139, Section 46 to plan, design, construct, improve and equip the Baahaali/Chichiltah regional solid waste collection and recycling center in Vanderwagen for the Baahaali chapter of the Navajo Nation in McKinley county is extended through fiscal year 2026.

     SECTION 112. BECENTI CHAPTER VETERANS CENTER CONSTRUCTION--CHANGE PURPOSE--GENERAL FUND.--The unexpended balance of the appropriation to the Indian affairs department in Subsection 26 of Section 25 of Chapter 199 of Laws 2023 to plan, design, construct, equip and furnish a veterans center in the Becenti chapter of the Navajo Nation in McKinley county shall not be expended for the original purpose but is changed to plan, design, construct, renovate and equip a multipurpose building in the Becenti chapter of the Navajo Nation in McKinley county.

     SECTION 113. GALLUP REGIONAL ANIMAL SHELTER CONSTRUCTION--CHANGE TO CHALLENGER AND TELSTAR ROAD IMPROVEMENTS--CHANGE AGENCY--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division in Subsection 282 of Section 35 of Chapter 81 of Laws 2020 to acquire property for and to plan, design, construct, furnish and equip a regional animal shelter in Gallup in McKinley county shall not be expended for the original purpose but is appropriated to the department of transportation to plan, design and construct improvements to Challenger road and Telstar road in the Church Rock chapter of the Navajo Nation in McKinley county. The time of expenditure is extended through fiscal year 2026.

     SECTION 114. COYOTE CANYON CHAPTER CEMETERY CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 12 of Section 22 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 71 to plan, design and construct a community cemetery, including water lines and power lines, in the Coyote Canyon chapter of the Navajo Nation in McKinley county is extended through fiscal year 2026.

     SECTION 115. CRYSTAL CHAPTER LAND USE MASTER PLAN DEVELOPMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project in Subsection 14 of Section 26 of Chapter 53 of Laws 2022 to develop a land use master plan for the Crystal chapter of the Navajo Nation in McKinley and San Juan counties is extended through fiscal year 2026.

     SECTION 116. OJO ENCINO CHAPTER EAGLE SPRING POWER LINE CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 48 of Section 70 of Chapter 81 of Laws 2020 for archaeological and environmental studies, to purchase easements and rights of way and to plan, design and construct the Eagle Spring power line for the Ojo Encino chapter of the Navajo Nation in McKinley and Sandoval counties is extended through fiscal year 2026.

     SECTION 117. PUEBLO PINTADO CHAPTER POWER LINE CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 14 of Section 20 of Chapter 81 of Laws 2016 and reauthorized in Laws 2020, Chapter 82, Section 51 and again in Laws 2022, Chapter 52, Section 69 to plan, design and construct a power line in the Pueblo Pintado chapter of the Navajo Nation in McKinley county is extended through fiscal year 2026.

     SECTION 118. MANUELITO CHAPTER POWER LINE AND HOUSE WIRING CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 29 of Section 70 of Chapter 81 of Laws 2020 to conduct archaeological and environmental studies and to plan, design and construct power lines and house wiring in the Manuelito chapter of the Navajo Nation in McKinley county is extended through fiscal year 2026.

     SECTION 119. LAKE VALLEY CHAPTER VEHICLE AND EQUIPMENT PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project in Subsection 70 of Section 26 of Chapter 53 of Laws 2022 to purchase and equip road equipment for the Lake Valley chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 120. LAKE VALLEY CHAPTER YELLOW POINT ROCK POWER LINE CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 66 of Section 70 of Chapter 81 of Laws 2020 for archaeological and environmental studies, to purchase easements and rights of way and to plan, design and construct the Yellow Point Rock power line in the Lake Valley chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 121. NAHODISHGISH CHAPTER HOUSE ACCESSIBILITY IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 17 of Section 22 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 73 to plan, design and construct accessibility improvements at the chapter house of the Nahodishgish chapter of the Navajo Nation in McKinley county is extended through fiscal year 2026.

     SECTION 122. NENAHNEZAD CHAPTER MULTIPURPOSE BUILDING ROOF RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 36 of Section 22 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 104 to plan, design, construct and renovate the roof on the multipurpose building in the Nenahnezad chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 123. TO'HAJIILEE CHAPTER POWER LINE EXTENSION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 4 of Section 70 of Chapter 81 of Laws 2020 to plan, design, construct and extend a power line at Platero's community in the To'hajiilee chapter of the Navajo Nation in Bernalillo county is extended through fiscal year 2026.

     SECTION 124. TOHATCHI CHAPTER POWER LINE EXTENSION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 16 of Section 20 of Chapter 81 of Laws 2016 and reauthorized in Laws 2020, Chapter 82, Section 54 and again in Laws 2022, Chapter 52, Section 70 to plan, design and construct power line extensions in the Tohatchi chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 125. TOHATCHI CHAPTER RED WILLOW FARM UTILITY AND ROAD IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 17 of Section 20 of Chapter 81 of Laws 2016 and reauthorized in Laws 2017, Chapter 133, Section 66 to plan, design, construct and make improvements to water lines, power lines and roads for Red Willow farm in the Tohatchi chapter of the Navajo Nation in McKinley county and for which the time of expenditure was extended in Laws 2020, Chapter 82, Section 55 and Laws 2022, Chapter 52, Section 75 is extended through fiscal year 2026.

     SECTION 126. TOHATCHI CHAPTER WAREHOUSE CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 19 of Section 22 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 76 to plan, design and construct a warehouse for the Tohatchi chapter of the Navajo Nation in McKinley county is extended through fiscal year 2026.

     SECTION 127. TSE'DAA'KAAN CHAPTER WATER LINE EXTENSION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project originally authorized in Subsection 89 of Section 26 of Chapter 81 of Laws 2020 and appropriated to the Indian affairs department in Laws 2021, Chapter 139, Section 65 to acquire easements and rights of way for and to plan, design and construct, including archaeological and environmental studies, a water line extension for the Tse'Daa'Kaan chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 128. SHEEPSPRINGS CHAPTER SCATTERED WATER LINE CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project originally authorized in Subsection 87 of Section 26 of Chapter 81 of Laws 2020 and appropriated to the Indian affairs department in Laws 2021, Chapter 139, Section 62 to acquire rights of way and to perform archaeological and environmental studies and to plan, design, construct and extend scattered water lines for the Sheepsprings chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 129. ACEQUIA CANONCITO DE LA CUEVA IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 9 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements to the acequia Canoncito de La Cueva in the Canoncito de La Cueva area in Mora county is extended through fiscal year 2026.

     SECTION 130. ACEQUIA DE LA ISLA MORPHY LAKE DAM EQUIPMENT PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 10 of Section 34 of Chapter 81 of Laws 2020 to purchase and install instrumentation to monitor water levels at Morphy Lake dam for the acequia de La Isla in Mora county is extended through fiscal year 2026.

     SECTION 131. ACEQUIA DEL ALTO AL NORTE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 13 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements to the acequia del Alto al Norte in Mora county is extended through fiscal year 2026.

     SECTION 132. CASSIDY DITCH IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 14 of Section 34 of Chapter 81 of Laws 2020 to plan, design, construct and install improvements to the Cassidy ditch in Mora county is extended through fiscal year 2026.

     SECTION 133. LEDOUX MUTUAL DOMESTIC WATER CONSUMERS ASSOCIATION WATER SYSTEM IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 55 of Section 26 of Chapter 81 of Laws 2020 to plan, design, construct and equip water system improvements for the Ledoux mutual domestic water consumers association in Mora county is extended through fiscal year 2026.

     SECTION 134. MORA COUNTY VETERANS' MEMORIAL CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 290 of Section 35 of Chapter 81 of Laws 2020 to plan, design and construct a veterans' memorial in Mora county is extended through fiscal year 2026.

     SECTION 135. ACEQUIA DEL DISTRITO IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 16 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements to the acequia del Distrito in Santa Fe and Rio Arriba counties is extended through fiscal year 2026.

     SECTION 136. NAVAJO NATION BROADBAND CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of information technology project in Subsection 2 of Section 31 of Chapter 81 of Laws 2020 to acquire easements and rights of way and to plan, design and construct improvements, including conducting archaeological and environmental studies and enhanced 911 and rural addressing, for the broadband internet access project across the Navajo Nation in McKinley, San Juan, Rio Arriba, Sandoval, Bernalillo, Cibola and Socorro counties is extended through fiscal year 2026.

     SECTION 137. LOS ALAMOS STATE OFFICE BUILDING CONSTRUCTION--CHANGE TO CONSTRUCT AN OFFICE BUILDING FOR NORTHERN NEW MEXICO--GENERAL FUND.--The unexpended balance of the appropriation to the capital program fund in Subsection 4 of Section 7 of Chapter 199 of Laws 2023 to purchase, plan, design, renovate, construct, furnish and equip a building to house state offices in Los Alamos in Los Alamos county shall not be expended for the original purpose but is changed to purchase, plan, design, renovate, construct, furnish and equip a building to house state offices in northern New Mexico, including Los Alamos, Sandoval, Rio Arriba, Mora, Santa Fe and Taos counties.

     SECTION 138. OJO ENCINO CHAPTER RURAL ADDRESSING SYSTEM CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 25 of Section 22 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 80 to plan, design and construct a rural addressing system in the Ojo Encino chapter of the Navajo Nation in Sandoval and McKinley counties is extended through fiscal year 2026.

     SECTION 139. NAGEEZI CHAPTER ELECTRIC POWER LINE EXTENSION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 23 of Section 20 of Chapter 81 of Laws 2016 and reauthorized in Laws 2020, Chapter 82, Section 59 and again in Laws 2022, Chapter 52, Section 68 to plan, design and construct the Eagle Spring power line in the Ojo Encino chapter of the Navajo Nation in Sandoval and McKinley counties is extended through fiscal year 2026.

     SECTION 140. ELEVENTH JUDICIAL DISTRICT COURT COURTROOM TECHNOLOGY PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the eleventh judicial district court project in Subsection 1 of Section 15 of Chapter 53 of Laws 2022 to plan, design, purchase, equip and install courtroom technology at the eleventh judicial district court buildings in McKinley and San Juan counties is extended through fiscal year 2026.

     SECTION 141. REDI NET BROADBAND INFRASTRUCTURE CONSTRUCTION--CHANGE AGENCY--EXTEND TIME--SEVERANCE TAX BONDS.--The agency for the department of information technology project originally authorized in Subsection 3 of Section 31 of Chapter 81 of Laws 2020 to plan, design, engineer, construct, purchase and equip broadband infrastructure in northern New Mexico is changed to the local government division. The time of expenditure is extended through fiscal year 2026.

     SECTION 142. ACEQUIA ARRIBA DE CANONES IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 18 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements, including splash walls and culverts, to the acequia Arriba de Canones in Rio Arriba county is extended through fiscal year 2026.

     SECTION 143. ACEQUIA DE ALCALDE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 19 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements, including erosion control structures, removal of top-heavy and native and/or non-native invasive tree species and for bank stabilization projects, for the acequia de Alcalde in Rio Arriba county is extended through fiscal year 2026.

     SECTION 144. ACEQUIA DE LA CANADA ANCHA IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 20 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements, including the replacement of a siphon, for the acequia de La Canada Ancha in Rio Arriba county is extended through fiscal year 2026.

     SECTION 145. ACEQUIA DE LA OTRA VANDA IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 22 of Section 34 of Chapter 81 of Laws 2020 to plan, design, purchase, construct and improve the acequia de La Otra Vanda in Rio Arriba county is extended through fiscal year 2026.

     SECTION 146. ACEQUIA DE LA PLAZA DE DIXON RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 23 of Section 34 of Chapter 81 of Laws 2020 to plan, design, construct and install improvements for restoration of the acequia de La Plaza de Dixon between New Mexico highways 75 and 68 in Rio Arriba county is extended through fiscal year 2026.

     SECTION 147. ACEQUIA DE LA PLAZA DE DIXON RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 24 of Section 34 of Chapter 81 of Laws 2020 to plan, design, construct and renovate improvements to the acequia de La Plaza de Dixon south of the Rio Embudo near New Mexico highway 75 in Rio Arriba county is extended through fiscal year 2026.

     SECTION 148. ACEQUIA DE LOS GARCIAS IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 28 of Section 34 of Chapter 81 of Laws 2020 to plan, design, construct, repair and improve, including desagues, the acequia de Los Garcias in Rio Arriba county is extended through fiscal year 2026.

     SECTION 149. ACEQUIA DE LOS GARCIAS PIPELINE INSTALLATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 29 of Section 34 of Chapter 81 of Laws 2020 to plan, design, construct and install improvements, including underground pipelines, for the acequia de Los Garcias in Rio Arriba county is extended through fiscal year 2026.

     SECTION 150. ACEQUIA DEL MEDIO IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 33 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements, including a sluice box, a headgate, pipeline and structures, for the acequia del Medio in Rio Arriba county is extended through fiscal year 2026.

     SECTION 151. ACEQUIA MESA DEL MEDIO RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 34 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements to the acequia Mesa del Medio in Rio Arriba county is extended through fiscal year 2026.

     SECTION 152. AGUA SANA WATER USERS' ASSOCIATION AND CHAMITA MUTUAL DOMESTIC WATER CONSUMERS AND SEWAGE WORKS ASSOCIATION INTERCONNECTION CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 63 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct an interconnection between the Agua Sana water users' association and the Chamita mutual domestic water consumers and sewage works association in Rio Arriba county is extended through fiscal year 2026.

     SECTION 153. JICARILLA APACHE NATION EMERGENCY MEDICAL SERVICES EQUIPMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project in Subsection 49 of Section 26 of Chapter 53 of Laws 2022 to purchase and equip vehicles and equipment, including an ambulance cot, for the Jicarilla emergency medical services in the Jicarilla Apache Nation in Rio Arriba county is extended through fiscal year 2026.

     SECTION 154. JICARILLA APACHE NATION EMERGENCY MEDICAL SERVICES VEHICLE PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 50 of Section 26 of Chapter 53 of Laws 2022 to purchase and equip vehicles and equipment for the Jicarilla emergency medical services in the Jicarilla Apache Nation in Rio Arriba county is extended through fiscal year 2026.

     SECTION 155. VALLECITOS EAST DITCH ASSOCIATION INFRASTRUCTURE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 39 of Section 34 of Chapter 81 of Laws 2020 to plan, design, repair and construct acequia improvements, including a diversion dam, for the Vallecitos east ditch association in Rio Arriba county is extended through fiscal year 2026.

     SECTION 156. VALLECITOS WEST DITCH ASSOCIATION IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 40 of Section 34 of Chapter 81 of Laws 2020 to plan, design, construct, repair and make improvements, including a diversion dam and a headwall, for the Vallecitos west ditch association in Rio Arriba county is extended through fiscal year 2026.

     SECTION 157. ACEQUIA DE LA POSECION PIPELINE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 25 of Section 34 of Chapter 81 of Laws 2020 to plan, design, construct and equip improvements to the acequia de La Posecion in Rio Arriba county is extended through fiscal year 2026.

     SECTION 158. FERRAN COMMUNITY DITCH ASSOCIATION IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 35 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct acequia improvements and repairs for the Ferran community ditch association in Rio Arriba county is extended through fiscal year 2026.

     SECTION 159. GREATER CHIMAYO MUTUAL DOMESTIC WATER CONSUMERS ASSOCIATION WATER DISTRIBUTION SYSTEM CONSTRUCTION--CHANGE TO PURCHASE RADIO READ METERS--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the department of environment in Subsection 61 of Section 22 of Chapter 53 of Laws 2022 to plan, design, construct, purchase and install water lines along county road 93 from New Mexico highway 76 to county road 87 for the greater Chimayo mutual domestic water consumers association in Rio Arriba county shall not be expended for the original purpose but is changed to purchase and equip radio read water meters and to replace touch units for the greater Chimayo mutual domestic water consumers association.

     SECTION 160. JICARILLA APACHE NATION SECURITY CAMERA PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project in Subsection 52 of Section 26 of Chapter 53 of Laws 2022 to purchase and equip security cameras for the supermarket in the Jicarilla Apache Nation in Dulce in Rio Arriba county is extended through fiscal year 2026.

     SECTION 161. ESPANOLA LIGHT-EMITTING DIODE LIGHTING INSTALLATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project in Subsection 17 of Section 38 of Chapter 81 of Laws 2020 to plan, design, purchase, construct and install light-emitting diode lighting citywide in Espanola in Rio Arriba county is extended through fiscal year 2026.

     SECTION 162. SAN JOAQUIN DEL RIO DE CHAMA LAND GRANT COMMUNITY CENTER CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 327 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, furnish and equip the San Joaquin del rio de Chama land grant-merced community center in Rio Arriba county is extended through fiscal year 2026.

     SECTION 163. TIERRA AMARILLA LAND GRANT LAND AND WATER RIGHTS ACQUISITION--CHANGE TO MULTIPURPOSE FACILITY CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The unexpended balance of the appropriation to the local government division in Subsection 356 of Section 28 of Chapter 199 of Laws 2023 to acquire land and water rights within the exterior boundaries of the land grant-merced de los Pueblos de Tierra Amarilla in Rio Arriba county shall not be expended for the original purpose but is changed to acquire land and to plan, design, purchase, construct, renovate, furnish and equip a multipurpose facility for the land grant-merced de los Pueblos de Tierra Amarilla. The time of expenditure is extended through fiscal year 2026.

     SECTION 164. ROOSEVELT COUNTY SPECIAL HOSPITAL DISTRICT SLEEP LABORATORY RENOVATION--CHANGE TO EQUIPMENT PURCHASE--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division in Subsection 334 of Section 30 of Chapter 53 of Laws 2022 to plan, design, construct, renovate and equip a sleep laboratory for the Roosevelt county special hospital district in Roosevelt county shall not be expended for the original purpose but is changed to purchase equipment, including information technology systems, for the Roosevelt county special hospital district.

     SECTION 165. ELIDA WASTEWATER SYSTEM CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 77 of Section 26 of Chapter 81 of Laws 2020 to plan, design, construct, furnish and equip a wastewater system in Elida in Roosevelt county is extended through fiscal year 2026.

     SECTION 166. BLOOMFIELD IRRIGATION DISTRICT SPILLGATE CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 44 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct a spillgate for the Citizens ditch and La Pumpa acequia for the Bloomfield irrigation district in San Juan county is extended through fiscal year 2026.

     SECTION 167. JONES CANYON SIPHON SYSTEM REPLACEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 24 of Section 29 of Chapter 53 of Laws 2022 to replace the Jones canyon siphon system on the Hillside irrigation ditch in San Juan county is extended through fiscal year 2026.

     SECTION 168. HUERFANO CHAPTER BATHROOM ADDITIONS AND WATER LINES CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 65 of Section 70 of Chapter 81 of Laws 2020 to acquire rights of way and easements, to conduct archaeological and environmental studies and to plan, design, construct and equip bathroom additions and the Carson north water line for the Huerfano chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 169. LAKE VALLEY CHAPTER POWER LINE EXTENSION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 35 of Section 22 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 72 to plan, design and construct power line extensions in the Lake Valley chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 170. BLUEWATER WATER AND SANITATION DISTRICT WATER AND WASTEWATER SYSTEM IMPROVEMENT--CHANGE TO NAVAJO ROUTES 5010 AND 342 IMPROVEMENTS--CHANGE AGENCY--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the department of environment in Subsection 12 of Section 26 of Chapter 81 of Laws 2020 to plan, design, construct, repair, purchase and equip and make improvements to the water and wastewater systems for the Bluewater water and sanitation district in Bluewater in Cibola county shall not be expended for the original purpose but is appropriated to the department of transportation to plan, design and construct road improvements to Navajo routes 5010 and 342 in the Tse Alnaozti'i' chapter of the Navajo Nation in San Juan county. The time of expenditure is extended through fiscal year 2026.

     SECTION 171. NAGEEZI CHAPTER ELECTRIC POWER LINE EXTENSION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project originally authorized in Subsection 33 of Section 20 of Chapter 81 of Laws 2016 and reauthorized in Laws 2020, Chapter 82, Section 73 and again in Laws 2022, Chapter 52, Section 106 to construct the Kinnadiz and Pillow Crest electrical powerline extension project in the Nageezi chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 172. NAVAJO DAM DOMESTIC WATER CONSUMERS AND MUTUAL SEWAGE WORKS COOPERATIVE FIREPROOF BUILDINGS CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 85 of Section 26 of Chapter 81 of Laws 2020 to plan, design, construct, purchase, install, replace, furnish and equip insulated fireproof steel buildings for the Navajo Dam domestic water consumers and mutual sewage works cooperative at Navajo Dam in San Juan county is extended through fiscal year 2026.

     SECTION 173. NAVAJO LAKE STATE PARK VEHICLE PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the state parks division of the energy, mineral and natural resources department project in Subsection 6 of Section 23 of Chapter 81 of Laws 2020 to purchase and equip vehicles and equipment and make improvements for Navajo Lake state park in San Juan county is extended through fiscal year 2026.

     SECTION 174. SAN JUAN COUNTY REGIONAL MEDICAL CENTER WOMEN'S INPATIENT AND CHILDBIRTH UNIT RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project originally authorized in Subsection 340 of Section 35 of Chapter 81 of Laws 2020 and reauthorized in Laws 2023, Chapter 203, Section 196 to plan, design, construct, renovate and equip the women's inpatient and childbirth unit, including room expansions and bathroom improvements, at the San Juan regional medical center in Farmington in San Juan county is extended through fiscal year 2026.

     SECTION 175. SAN JUAN COUNTY SHERIFF'S OFFICE HELICOPTER PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 337 of Section 30 of Chapter 53 of Laws 2022 to purchase and equip a helicopter for the sheriff's office in San Juan county is extended through fiscal year 2026.

     SECTION 176. SHIPROCK CHAPTER EMERGENCY RESPONSE COMMAND CENTER CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 75 of Section 70 of Chapter 81 of Laws 2020 to plan, design, construct and equip an emergency response command center on the south side of the San Juan river in the Shiprock chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 177. SHIPROCK CHAPTER WASTEWATER SYSTEM CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project originally authorized in Subsection 59 of Section 18 of Chapter 81 of Laws 2016 and reauthorized in Laws 2020, Chapter 82, Section 74 and appropriated to the Indian affairs department in Laws 2021, Chapter 139, Section 64 and for which the time of expenditure was extended in Laws 2022, Chapter 52, Section 100 to acquire rights of way and easements and to plan, design and construct a wastewater system and extension south of Shiprock in the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 178. ELEVENTH JUDICIAL DISTRICT ELECTRONIC ACCESS CONTROL SYSTEMS--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the eleventh judicial district court project in Subsection 3 of Section 19 of Chapter 81 of Laws 2020 to plan, design, construct, replace and install an electronic access control system at the eleventh judicial district courthouse in Aztec in San Juan county is extended through fiscal year 2026.

     SECTION 179. AZTEC OUTDOOR RECREATION MANUFACTURING AND RETAIL FACILITY CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 334 of Section 35 of Chapter 81 of Laws 2020 to acquire property for and to plan, design, construct, furnish and equip an outdoor recreation, manufacturing and retail facility in Aztec in San Juan county is extended through fiscal year 2026.

     SECTION 180. AZTEC WATER LINE RELOCATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 81 of Section 26 of Chapter 81 of Laws 2020 to acquire utility easements and to plan, design and construct water lines along New Mexico highway 173 in Aztec in San Juan county is extended through fiscal year 2026.

     SECTION 181. EAST AZTEC ARTERIAL CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of transportation project originally authorized in Subsection 63 of Section 25 of Chapter 66 of Laws 2014 to construct the east Aztec arterial route in Aztec in San Juan county and reauthorized in Laws 2018, Chapter 68, Section 98 and reauthorized again in Laws 2020, Chapter 82, Section 70 to include planning and design for that route and for which the time of expenditure was extended in Laws 2022, Chapter 52, Section 101 is extended through fiscal year 2026.

     SECTION 182. SAN JUAN COUNTY NORTH STAR/EAST CULPEPPER FLATS WATER LINE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 80 of Section 26 of Chapter 81 of Laws 2020 to acquire rights of way and to plan, design and construct water system improvements, including a water pipeline and water line, from the North Star system at Aztec along New Mexico highway 574 to San Juan county road 1350 for phase one of the Aztec/La Plata regional pipeline project in San Juan county is extended through fiscal year 2026.

     SECTION 183. ELEVENTH JUDICIAL DISTRICT COURT FARMINGTON COURT EQUIPMENT--CHANGE TO RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the eleventh judicial district court in Subsection 2 of Section 15 of Chapter 53 of Laws 2022 to plan, design, construct, renovate and equip improvements, including safety and security upgrades, at the eleventh judicial district court in Farmington in San Juan county shall not be expended for the original purpose but is changed to plan, design, construct, renovate and equip the court facility in Farmington. The time of expenditure is extended through fiscal year 2026.

     SECTION 184. FARMINGTON CHILLER PLANT INFRASTRUCTURE REPLACEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 83 of Section 26 of Chapter 81 of Laws 2020 to plan, design, construct, purchase, install and replace a plant cooling tower, including emergency power transfer switches and building automation systems, in Farmington in San Juan county is extended through fiscal year 2026.

     SECTION 185. NASCHITTI CHAPTER POWER LINE CONSTRUCTION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 67 of Section 70 of Chapter 81 of Laws 2020 to plan, design and construct power line extensions in the Naschitti chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 186. SHIPROCK CHAPTER WATER AND WASTEWATER LINE CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project originally authorized in Subsection 88 of Section 26 of Chapter 81 of Laws 2020 and appropriated to the Indian affairs department in Laws 2021, Chapter 139, Section 63 to plan, design and construct water and wastewater lines on the south side of Shiprock in the Shiprock chapter of the Navajo Nation in San Juan county is extended through fiscal year 2026.

     SECTION 187. SMITH LAKE CHAPTER PARKING LOT IMPROVEMENT--CHANGE TO VETERANS' BUILDING PARKING LOT--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the Indian affairs department originally authorized in Subsection 18 of Section 22 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 78 to plan and design parking lots, including curbs and lighting, for the chapter complex in the Smith Lake chapter of the Navajo Nation in McKinley county shall not be expended for the original or reauthorized purpose but is changed to plan, design and construct parking lots, including curbs and lighting, for a veterans' building in the chapter complex in the Smith Lake chapter. The time of expenditure is extended through fiscal year 2026.

     SECTION 188. ACEQUIA DE LOS SEGURAS IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 45 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements, including bank stabilization, for the acequia de Los Seguras in San Miguel county is extended through fiscal year 2026.

     SECTION 189. ACEQUIA MADRE DE EL CERRITO PIPE PURCHASE--CHANGE TO ACEQUIA IMPROVEMENT--GENERAL FUND.--The unexpended balance of the appropriation to the interstate stream commission in Subsection 39 of Section 27 of Chapter 199 of Laws 2023 to purchase and equip piping for the acequia Madre de el Cerrito in San Miguel county shall not be expended for the original purpose but is changed to plan, design, construct, improve and equip the acequia Madre de el Cerrito in San Miguel county.

     SECTION 190. EL VALLE WATER ALLIANCE STORAGE TANK CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 93 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct a water storage tank for El Valle water alliance in San Miguel county is extended through fiscal year 2026.

     SECTION 191. PECOS WATER AND WASTEWATER LINE CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 96 of Section 26 of Chapter 81 of Laws 2020 to plan, design, construct, upgrade, purchase and equip water and sewer lines in Pecos in San Miguel county is extended through fiscal year 2026.

     SECTION 192. SAN MIGUEL DEL BADO LAND GRANT CENTER IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 344 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, furnish, purchase and equip improvements to the San Miguel del Bado land grant-merced center in San Miguel county is extended through fiscal year 2026.

     SECTION 193. PASEO DEL VOLCAN RIGHTS-OF-WAY ACQUISITION AND CONSTRUCTION--CHANGE TO SANDOVAL COUNTY PASEO DEL VOLCAN CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The following projects shall not be expended for the original or reauthorized purposes but are changed to acquire easements and rights of way for and to plan, design and construct paseo del Volcan in Sandoval county, and the time of expenditure is extended through fiscal year 2026:

          A. the department of transportation project originally authorized in Subsection 57 of Section 25 of Chapter 66 of Laws 2014 and reauthorized in Laws 2018, Chapter 68, Section 3 and for which the time of expenditure was extended in Laws 2020, Chapter 82, Section 3 and reauthorized in Laws 2022, Chapter 52, Section 3 to acquire rights of way for and to plan, design and construct paseo del Volcan in Bernalillo and Sandoval counties;

          B. the department of transportation project originally authorized in Subsection 1 of Section 32 of Chapter 80 of Laws 2018 and reauthorized in Laws 2022, Chapter 52, Section 4 to acquire rights of way and to design and construct paseo del Volcan, also known as New Mexico highway 347, in Sandoval and Bernalillo counties;

          C. the department of transportation project originally authorized in Subsection 1 of Section 24 of Chapter 81 of Laws 2016 and for which the time of expenditure was extended in Laws 2020, Chapter 82, Section 4 and reauthorized in Laws 2022, Chapter 52, Section 5 to acquire rights of way and to design and construct paseo del Volcan, also known as New Mexico highway 347, in Sandoval and Bernalillo counties;

          D. the department of transportation project originally authorized in Subsection 61 of Section 24 of Chapter 81 of Laws 2016 and for which the time of expenditure was extended in Laws 2020, Chapter 82, Section 79 and reauthorized in Laws 2022, Chapter 52, Section 6 to acquire rights of way and to plan, design and construct paseo del Volcan in Bernalillo and Sandoval counties; and

          E. the department of transportation project originally authorized in Subsection 106 of Section 40 of Chapter 277 of Laws 2019 and reauthorized in Laws 2023, Chapter 203, Section 5 to acquire rights of way for and to plan, design and construct paseo del Volcan, also known as New Mexico highway 347, in Bernalillo and Sandoval counties.

     SECTION 194. CORRALES WASTEWATER BYPASS AND COLLECTION SYSTEM CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 108 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct a wastewater emergency bypass and collection system for Corrales in Sandoval county is extended through fiscal year 2026.

     SECTION 195. SANDOVAL COUNTY THERAPEUTIC RIDING FACILITY IMPROVEMENT--CHANGE TO PURCHASE VEHICLES AND EQUIPMENT--EXTEND TIME--GENERAL FUND.--The unexpended balance of the appropriation to the local government division in Subsection 409 of Section 28 of Chapter 199 of Laws 2023 to plan, design, construct, repair and improve the roofs at a therapeutic riding facility for children and adults with disabilities in Corrales in Sandoval county shall not be expended for the original purpose but is changed to purchase vehicles and equipment for a therapeutic riding facility in Corrales in Sandoval county. The time of expenditure is extended through fiscal year 2026.

     SECTION 196. JEMEZ SPRINGS WASTEWATER TREATMENT PLANT EQUIPMENT--CHANGE TO WASTEWATER TREATMENT PLANT AND COLLECTION SYSTEM IMPROVEMENTS--GENERAL FUND.--The unexpended balance of the appropriation to the department of environment in Subsection 105 of Section 19 of Chapter 199 of Laws 2023 to plan, design, construct, purchase and improve operational equipment for the wastewater treatment plant in Jemez Springs in Sandoval county is changed to plan, design, construct, purchase, equip and improve the wastewater treatment plant and collection system in Jemez Springs.

     SECTION 197. ASK ACADEMY CHARTER SCHOOL IMPROVEMENT--EXPAND PURPOSE--GENERAL FUND.--The public education department project in Subsection 192 of Section 16 of Chapter 199 of Laws 2023 to plan, design, construct, furnish and equip improvements to buildings and grounds at the ASK Academy charter school, including fencing, information technology, security infrastructure and installation of related equipment, in Rio Rancho in Sandoval county may include the purchase of property, buildings and equipment.

     SECTION 198. RIO RANCHO LOMA COLORADO MAIN LIBRARY ROOF REPLACEMENT--CHANGE TO SERVICE DESK RENOVATION--GENERAL FUND.--The unexpended balance of the appropriation to the local government division in Subsection 420 of Section 28 of Chapter 199 of Laws 2023 to plan, design, construct and replace the roof at the Loma Colorado main library in Rio Rancho in Sandoval county shall not be expended for the original purpose but is changed to renovate and furnish service desks at the Loma Colorado main library and the Esther Bone memorial library in Rio Rancho in Sandoval county.

     SECTION 199. ACEQUIA DE LA OTRA BANDA IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 56 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements, including a diversion, to the acequia de La Otra Banda in Santa Fe county is extended through fiscal year 2026.

     SECTION 200. ACEQUIA DEL CANO IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 59 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements to the acequia del Cano in Santa Fe county is extended through fiscal year 2026.

     SECTION 201. ACEQUIA LARGA DE JACONA BARRIER CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 62 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements, including a concrete canvas barrier, for the acequia Larga de Jacona in Santa Fe county is extended through fiscal year 2026.

     SECTION 202. DEPARTMENT OF PUBLIC SAFETY FIRING RANGE IMPROVEMENTS--CHANGE TO IMPROVE A REALITY-BASED TRAINING FACILITY--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund in Subsection 5 of Section 8 of Chapter 81 of Laws 2020 to plan and design infrastructure and site improvements, including utilities, restrooms, lighting and acoustic controls, at the firing range operated and maintained by the department of public safety in Santa Fe county shall not be expended for the original purpose but is changed to plan, design, construct, furnish and equip improvements to the department of public safety's statewide reality-based training facility to support compliance with training standards set for law enforcement agencies and maintained by the department of public safety. The time of expenditure is extended through fiscal year 2026.

     SECTION 203. MCCURDY COMMUNITY FACILITIES DEVELOPMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 390 of Section 30 of Chapter 53 of Laws 2022 to remediate and demolish existing facilities and to prepare a site for redevelopment of community facilities in Espanola in Santa Fe county is extended through fiscal year 2026.

     SECTION 204. RIO CHIQUITO MUTUAL DOMESTIC WATER CONSUMERS AND MUTUAL SEWAGE WORKS ASSOCIATION WATER SYSTEM IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 118 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct water system improvements, including a water storage tank, for the Rio Chiquito mutual domestic water consumers and mutual sewage works association in Santa Fe county is extended through fiscal year 2026.

     SECTION 205. SANTA FE COUNTY YOUTH DEVELOPMENT FACILITY CONVERSION--CHANGE TO COUNTY CLERK'S WAREHOUSE--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division in Subsection 397 of Section 30 of Chapter 53 of Laws 2022 to plan, design, construct and renovate the Santa Fe county youth development facility, including converting space for use as the county clerk elections warehouse and for secure long-term document storage and related equipment, in Santa Fe county shall not be expended for the original purpose but is changed to plan, design, construct, renovate and equip space for use as the county clerk's elections warehouse and secure long-term document storage facility in Santa Fe county.

     SECTION 206. SANTA FE COUNTY CLERK'S OFFICE STORAGE FACILITY IMPROVEMENT--CHANGE TO ELECTIONS WAREHOUSE RENOVATION--GENERAL FUND.--The unexpended balance of the appropriation to the local government division in Subsection 441 of Section 28 of Chapter 199 of Laws 2023 to plan, design, construct, renovate and equip an area at the juvenile detention center for use as a storage facility for voting machines, elections equipment and vital records by the county clerk's office, including security, technology, broadband, heating, ventilation, air conditioning and fire suppression systems, in Santa Fe in Santa Fe county shall not be expended for the original purpose but is changed to plan, design, construct, renovate and equip space for use as the county clerk's office elections warehouse and long-term document storage facility in Santa Fe county.

     SECTION 207. FIRST JUDICIAL DISTRICT ATTORNEY'S OFFICE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the office of the first judicial district attorney project originally authorized in Section 12 of Chapter 81 of Laws 2020 and reauthorized in Laws 2022, Chapter 52, Section 120 to purchase, equip and install telecommunications systems, security systems, information technology, furniture and office equipment, including partitions and fixtures, in the first judicial district court in Santa Fe in Santa Fe county is extended through fiscal year 2026.

     SECTION 208. CHILDREN, YOUTH AND FAMILIES DEPARTMENT THERAPEUTIC GROUP HOMES CONSTRUCTION--CHANGE TO ACQUISITION AND CONSTRUCTION OF PROPERTY STATEWIDE--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund in Subsection 15 of Section 8 of Chapter 53 of Laws 2022 to acquire, plan, design, construct, renovate, equip and furnish therapeutic group homes for the children, youth and families department statewide shall not be expended for the original purpose but is changed to acquire property for and to plan, design, construct, repair, renovate, furnish and equip improvements for children, youth and families department facilities statewide.

     SECTION 209. CHILDREN, YOUTH AND FAMILIES DEPARTMENT HUMAN TRAFFICKING SAFE HOUSE IMPROVEMENT--CHANGE TO PROPERTY ACQUISITION AND IMPROVEMENTS STATEWIDE--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund in Subsection 14 of Section 8 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, improve and equip a safe place to live for youth who are human trafficking victims at a facility and location to be determined by the children, youth and families department shall not be expended for the original purpose but is changed to acquire property and to plan, design, construct, repair, renovate, furnish and equip improvements for children, youth and families department facilities statewide. The time of expenditure is extended through fiscal year 2026.

     SECTION 210. ELDORADO AREA WATER AND SANITATION DISTRICT PARKING LOT SOLAR CANOPY CONSTRUCTION--EXPAND PURPOSE--GENERAL FUND.--The local government division project in Subsection 428 of Section 28 of Chapter 199 of Laws 2023 to plan, design and construct a solar canopy over the maintenance vehicle parking lot at the district administration building for the Eldorado area water and sanitation district in Santa Fe county may include planning, designing and constructing a solar canopy at a field workshop parking lot for the district.

     SECTION 211. GREATER GLORIETA COMMUNITY MUTUAL DOMESTIC WATER CONSUMERS AND SEWAGE WORKS ASSOCIATION WELL DRILLING--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 117 of Section 26 of Chapter 81 of Laws 2020 to plan, design, construct, purchase, equip and install a drinking water project for the greater Glorieta community regional mutual domestic water consumers and sewage works in Santa Fe county is extended through fiscal year 2026.

     SECTION 212. HOMELAND SECURITY AND EMERGENCY MANAGEMENT DEPARTMENT WAREHOUSE CONSTRUCTION--CHANGE AGENCY--SEVERANCE TAX BONDS.--The agency for the homeland security and emergency management department project in Laws 2022, Chapter 53, Section 25 to plan, design, construct, purchase and equip a warehouse storage building at the homeland security and emergency management department in Santa Fe in Santa Fe county is changed to the facilities management division of the general services department.

     SECTION 213. ROMERO PARK AREA WATER LINE SYSTEM EXTENSION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the department of environment project in Subsection 14 of Section 66 of Chapter 81 of Laws 2020 to plan, design and construct meters and water line system extensions to provide service for Romero park, La Familia, the Nancy Rodriguez community center and the Agua Fria fire station in Santa Fe county is extended through fiscal year 2026.

     SECTION 214. SECRETARY OF STATE BALLOT SORTING AND SCANNING SYSTEM PURCHASE--CHANGE AGENCY--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the office of the secretary of state in Laws 2022, Chapter 53, Section 32 to purchase, equip and install a vote-by-mail ballot sorting and scanning system for the office of the secretary of state in Santa Fe county shall not be expended for the original purpose but is appropriated to the local government division to purchase, equip and install a vote-by-mail ballot sorting and scanning system for the county clerk's office in Santa Fe county. The time of expenditure is extended through fiscal year 2026.

     SECTION 215. SANTA FE COUNTY RECOVERY CENTER PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project originally authorized in Subsection 385 of Section 35 of Chapter 81 of Laws 2020 and reauthorized in Laws 2022, Chapter 52, Section 123 to purchase land and buildings and to plan, design, construct, renovate, furnish and equip a facility for a recovery program in Santa Fe county is extended through fiscal year 2026.

     SECTION 216. SANTA FE COUNTY RECOVERY PROGRAM BUILDING PURCHASE--EXTEND TIME--GENERAL FUND.--The time of expenditure for the local government division project originally authorized in Subsection 386 of Section 34 of Chapter 277 of Laws 2019 and reauthorized in Laws 2022, Chapter 52, Section 116 to purchase land and buildings and to plan, design, construct, renovate, furnish and equip a facility for a recovery program in Santa Fe county is extended through fiscal year 2026.

     SECTION 217. SANTA FE EL MUSEO CULTURAL FACILITY IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 390 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, furnish, equip and install improvements, including roofing, lighting and heating, ventilation and air conditioning systems, to El Museo Cultural de Santa Fe in Santa Fe in Santa Fe county is extended through fiscal year 2026.

     SECTION 218. SANTA FE HOMEBOUND MEALS PROGRAM FACILITY IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 394 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, purchase, furnish, equip and install improvements, including information technology and related equipment, furniture and infrastructure, for a meals program serving homebound and special needs individuals in Santa Fe in Santa Fe county is extended through fiscal year 2026.

     SECTION 219. SANTA FE MUNICIPAL COURT RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 396 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, furnish and equip renovations, including air conditioning and roof repairs, to the municipal court in Santa Fe in Santa Fe county is extended through fiscal year 2026.

     SECTION 220. SANTA FE SUPPORTIVE HOUSING FACILITIES RENOVATION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 401 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct and renovate a facility for homeless and below-market renters, including housing and services, in Santa Fe in Santa Fe county is extended through fiscal year 2026.

     SECTION 221. STATE LAND OFFICE LIGHTING AND CEILING REPLACEMENT--CHANGE TO RENOVATE BATHROOMS--EXTEND TIME--STATE LANDS MAINTENANCE FUND.--The unexpended balance of the appropriation to the state land office in Laws 2020, Chapter 81, Section 86 to plan, design and install energy-efficient lighting and for ceiling replacement at the state land office in Santa Fe in Santa Fe county shall not be expended for the original purpose but is changed to plan, design, construct and renovate the bathroom facilities at the state land office in Santa Fe in Santa Fe county. The time of expenditure is extended through fiscal year 2026.

     SECTION 222. SANTA FE STATE POLICE DISTRICT OFFICE CONSTRUCTION--EXTEND TIME--CAPITAL BUILDINGS REPAIR FUND.--The time of expenditure for the capital program fund project in Laws 2018, Chapter 80, Section 54 for which the time of expenditure was previously extended in Laws 2022, Chapter 52, Section 124 to plan, design, construct, renovate, furnish and equip a new state police district office in Santa Fe in Santa Fe county is extended through fiscal year 2026.

     SECTION 223. VETERANS' SERVICES DEPARTMENT VETERANS CEMETERY SITE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the veterans' services department project originally authorized in Laws 2014, Chapter 66, Section 34 and reauthorized in Laws 2016, Chapter 83, Section 104 to match federal funding to plan, design and construct regional veterans cemeteries statewide is extended through fiscal year 2030.

     SECTION 224. SANTA FE PUBLIC SCHOOL DISTRICT INFORMATION TECHNOLOGY UPGRADE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the public education department project in Subsection 206 of Section 18 of Chapter 53 of Laws 2022 to provide connectivity and infrastructure upgrades with district-wide area network fiber-optic lines for preschool and for mainframe distribution rooms at central offices, the educational service center and the B.F. Young building in the Santa Fe public school district in Santa Fe county is extended through fiscal year 2026.

     SECTION 225. SPACEPORT AMERICA PAYLOAD PROCESSING, INFORMATION TECHNOLOGY AND VISITOR ACCESS CONTROL CENTER CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the spaceport authority project in Laws 2020, Chapter 81, Section 37 to plan, design, construct and equip a payload processing center, an information technology building and a visitor access control facility at spaceport America in Sierra county is extended through fiscal year 2026.

     SECTION 226. SUNSET RIDGE ROAD IMPROVEMENT--CHANGE TO ROAD IMPROVEMENTS--GENERAL FUND.--The unexpended balance of the appropriation to the department of transportation in Subsection 96 of Section 33 of Chapter 199 of Laws 2023 to plan, design, construct and improve Sunset Ridge road in Elephant Butte in Sierra county shall not be expended for the original purpose but is changed to plan, design, construct, repair and improve roads in Elephant Butte.

     SECTION 227. ALAMO CHAPTER SATELLITE INTERNET INFORMATION TECHNOLOGY PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the Indian affairs department project in Subsection 106 of Section 26 of Chapter 53 of Laws 2022 to plan, design, purchase and install information technology for the Alamo chapter of the Navajo Nation in Socorro county is extended through fiscal year 2026.

     SECTION 228. ACEQUIA DE LA JOYA IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 55 of Section 34 of Chapter 81 of Laws 2020 to plan, design and construct improvements to the acequia de la Joya in Socorro county is extended through fiscal year 2026.

     SECTION 229. NEW MEXICO INSTITUTE OF MINING AND TECHNOLOGY ELECTRONIC LOCK SYSTEM CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the New Mexico institute of mining and technology project in Subsection 2 of Section 42 of Chapter 81 of Laws 2020 to plan, design, construct and equip an electronic door lock system campuswide on the New Mexico institute of mining and technology campus in Socorro in Socorro county is extended through fiscal year 2026.

     SECTION 230. ADMINISTRATIVE OFFICE OF THE COURTS MAGISTRATE AND DISTRICT COURTS SECURITY EQUIPMENT PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the administrative office of the courts project originally authorized in Laws 2018, Chapter 80, Section 3 and reauthorized in Laws 2022, Chapter 52, Section 121 to purchase and install security systems and for technology upgrades to security systems at magistrate courts and judicial district courts statewide is extended through fiscal year 2026.

     SECTION 231. CHILDREN, YOUTH AND FAMILIES DEPARTMENT THERAPEUTIC GROUP HOMES CONSTRUCTION--CHANGE TO ACQUISITION AND CONSTRUCTION OF PROPERTY STATEWIDE--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund originally authorized in Subsection 13 of Section 8 of Chapter 53 of Laws 2022 and reauthorized in Laws 2023, Chapter 203, Section 276 to acquire property and to plan, design, construct, renovate, equip and furnish therapeutic group homes for the children, youth and families department shall not be expended for the original or reauthorized purpose but is changed to acquire property and to plan, design, construct, repair, renovate, furnish and equip improvements for children, youth and families department facilities statewide.

     SECTION 232. CHILDREN, YOUTH AND FAMILIES DEPARTMENT THERAPEUTIC GROUP HOMES CONSTRUCTION--CHANGE TO ACQUISITION AND CONSTRUCTION OF PROPERTY STATEWIDE--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund originally authorized in Subsection 14 of Section 8 of Chapter 53 of Laws 2022 and reauthorized in Laws 2023, Chapter 203, Section 275 to acquire property and to plan, design, construct, renovate, equip and furnish therapeutic group homes for the children, youth and families department shall not be expended for the original or reauthorized purpose but is changed to acquire property and to plan, design, construct, repair, renovate, furnish and equip improvements for children, youth and families department facilities statewide.

     SECTION 233. CAMINO NUEVO AND JOHN PAUL TAYLOR YOUTH CENTERS IMPROVEMENTS--CHANGE TO CHILDREN, YOUTH AND FAMILIES DEPARTMENT FACILITIES STATEWIDE--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund in Subsection 2 of Section 8 of Chapter 81 of Laws 2020 to plan, design, construct, repair and renovate facilities, including upgrading exterior and interior wall finishing and stucco, and to make other improvements at the youth diagnostic and development center and Camino Nuevo youth center facilities in Albuquerque in Bernalillo county and at the John Paul Taylor center in Las Cruces in Dona Ana county shall not be expended for the original purpose but is changed to acquire property for and to plan, design, construct, repair, renovate, furnish and equip improvements for children, youth and families department facilities statewide. The time of expenditure is extended through fiscal year 2026.

     SECTION 234. DEPARTMENT OF PUBLIC SAFETY OFFICE BUILDING CONSTRUCTION--CHANGE PURPOSE--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund in Subsection 6 of Section 8 of Chapter 81 of Laws 2020 to plan, design, construct, furnish and equip a new state police district office in Santa Fe in Santa Fe county shall not be expended for the original purpose but is changed to plan, design, construct, renovate, furnish and equip infrastructure improvements at state police facilities statewide. The time of expenditure is extended through fiscal year 2026.

     SECTION 235. EARLY CHILDHOOD WELLNESS CENTER IMPROVEMENT--CHANGE TO EARLY CHILDHOOD EDUCATION AND CARE DEPARTMENT FACILITY IMPROVEMENTS STATEWIDE--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund in Subsection 1 of Section 9 of Chapter 138 of Laws 2021 to plan, design, construct, improve, repair, renovate, furnish and equip the child wellness center in Albuquerque in Bernalillo county shall not be expended for the original purpose but is changed to plan, design, construct, renovate, improve and equip early childhood education and care department facilities statewide. The time of expenditure is extended through fiscal year 2026.

     SECTION 236. STATEWIDE FACILITY DECOMMISSIONING AND DEMOLITION--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the capital program fund project in Subsection 12 of Section 8 of Chapter 81 of Laws 2020 to decommission and demolish buildings, including abatement of hazardous materials, and other programmatic renovations and construction at state-owned facilities statewide is extended through fiscal year 2026.

     SECTION 237. HOMELAND SECURITY AND EMERGENCY MANAGEMENT DEPARTMENT BUILDING IMPROVEMENT--CHANGE TO CONSTRUCT AND IMPROVE FACILITIES STATEWIDE--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund in Subsection 4 of Section 8 of Chapter 81 of Laws 2020 to plan, design, renovate and replace electrical systems, roofing and flooring at the homeland security and emergency management department in Santa Fe in Santa Fe county shall not be expended for the original purpose but is changed to plan, design, construct, renovate, improve and equip facilities at the homeland security and emergency management department statewide. The time of expenditure is extended through fiscal year 2026.

     SECTION 238. MAINSTREET ARTS AND CULTURAL DISTRICT IMPROVEMENT STATEWIDE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the economic development department project in Laws 2020, Chapter 81, Section 21 to plan, design and construct infrastructure improvements in mainstreet districts and local arts and cultural districts statewide is extended through fiscal year 2026.

     SECTION 239. SCHOOL BUS CAMERA PURCHASE--EXTEND TIME--PUBLIC SCHOOL CAPITAL OUTLAY FUND.--The time of expenditure for the public education department project in Subsection 2 of Section 49 of Chapter 53 of Laws 2022 to purchase, install and equip district-owned school buses with cameras statewide is extended through fiscal year 2026.

     SECTION 240. SCHOOL BUS REPLACEMENT STATEWIDE--EXTEND TIME--PUBLIC SCHOOL CAPITAL OUTLAY FUND.--The time of expenditure for the public education department project in Subsection 3 of Section 49 of Chapter 53 of Laws 2022 to purchase, replace and equip school buses for school districts statewide is extended through fiscal year 2026.

     SECTION 241. WORKFORCE SOLUTIONS DEPARTMENT OFFICE INFRASTRUCTURE IMPROVEMENT--CHANGE TO CONSTRUCTION--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the capital program fund in Subsection 21 of Section 8 of Chapter 53 of Laws 2022 to plan, design, repair and replace infrastructure at workforce solutions department offices statewide shall not be expended for the original purpose but is changed to plan, design, construct, renovate, improve and equip infrastructure at workforce solutions department offices statewide. The time of expenditure is extended through fiscal year 2026.

     SECTION 242. ACEQUIA DE LA SEBADILLA IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 68 of Section 34 of Chapter 81 of Laws 2020 to plan, design, construct and improve, including encasement, a section of the acequia de La Sebadilla for the acequias de Chamisal y Ojito in Taos county is extended through fiscal year 2026.

     SECTION 243. ACEQUIA DEL LLANO DE SAN MIGUEL IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 70 of Section 34 of Chapter 81 of Laws 2020 to plan, design, construct, repair and improve the acequia del Llano de San Miguel in Taos county is extended through fiscal year 2026.

     SECTION 244. CHAMISAL MUTUAL DOMESTIC WATER CONSUMERS ASSOCIATION INFRASTRUCTURE IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 126 of Section 26 of Chapter 81 of Laws 2020 to plan, design and construct improvements to infrastructure, including the painting of a water tank and installation of fencing and culverts, for the Chamisal mutual domestic water consumers association in Taos county is extended through fiscal year 2026.

     SECTION 245. CHAMISAL MUTUAL DOMESTIC WATER CONSUMERS ASSOCIATION WATER METER SYSTEM REPLACEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the department of environment project in Subsection 127 of Section 26 of Chapter 81 of Laws 2020 to plan, design, construct, furnish and equip the replacement of the water metering system for the Chamisal mutual domestic water consumers association in Taos county is extended through fiscal year 2026.

     SECTION 246. LAS ACEQUIAS DE LAS TRAMPAS IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the interstate stream commission project in Subsection 72 of Section 34 of Chapter 81 of Laws 2020 to plan, design, repair, construct and make improvements, including a diversion dam, the purchase and installation of ditch lining and reinforcement of the ditch banks, to las acequias de Las Trampas in Taos county is extended through fiscal year 2026.

     SECTION 247. SANTO TOMAS APOSTOL DEL RIO DE LAS TRAMPAS LAND GRANT-MERCED EQUIPMENT PURCHASE--CHANGE TO IMPROVE PLAZA PARKING--EXTEND TIME--GENERAL FUND.--The unexpended balance of the appropriation to the local government division in Subsection 475 of Section 28 of Chapter 199 of Laws 2023 to purchase and equip a wood processor and trailer for the Santo Tomas Apostol del Rio de las Trampas land grant-merced in Taos county shall not be expended for the original purpose but is changed to plan, design, construct and improve the plaza parking lot of the Santo Tomas Apostol del Rio de las Trampas land grant-merced. The time of expenditure is extended through fiscal year 2026.

     SECTION 248. QUESTA LIBRARY AND PARKING LOT IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 417 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct, renovate, furnish and equip improvements to the public library and parking area in Questa in Taos county is extended through fiscal year 2026.

     SECTION 249. QUESTA EQUIPMENT AND VEHICLE PURCHASE--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 429 of Section 30 of Chapter 53 of Laws 2022 to purchase and equip vehicles and equipment for the public works department in Questa in Taos county is extended through fiscal year 2026.

     SECTION 250. TAOS REGIONAL AIRPORT IMPROVEMENT--EXTEND TIME--SEVERANCE TAX BONDS.--The time of expenditure for the local government division project in Subsection 424 of Section 35 of Chapter 81 of Laws 2020 to plan, design, construct and equip improvements to the Taos regional airport in Taos in Taos county is extended through fiscal year 2026.

     SECTION 251. UNION COUNTY COURTHOUSE RENOVATION--CHANGE TO RENOVATE A JUDICIAL COMPLEX AND A LAW ENFORCEMENT COMPLEX--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division in Subsection 448 of Section 30 of Chapter 53 of Laws 2022 to plan, design, construct, furnish, renovate and equip improvements to the Union county courthouse for a judicial and law enforcement complex in Clayton in Union county shall not be expended for the original purpose but is changed to plan, design, construct, renovate, furnish and equip a judicial complex and a law enforcement complex in Clayton.

     SECTION 252. VALENCIA COUNTY ABANDONED PROPERTY ABATEMENT--CHANGE TO BUILDING DEMOLITION--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the appropriation to the local government division in Subsection 449 of Section 35 of Chapter 81 of Laws 2020 for abatement of abandoned properties in Valencia county shall not be expended for the original purpose but is changed to plan, design, construct, improve, demolish and remove abandoned buildings on properties under abatement in Valencia county. The time of expenditure is extended through fiscal year 2026.

     SECTION 253. VALENCIA COUNTY RAILROAD QUIET ZONES CONSTRUCTION--EXPAND PURPOSE--EXTEND TIME--SEVERANCE TAX BONDS.--The department of transportation project originally authorized in Subsection 21 of Section 38 of Chapter 81 of Laws 2020 and reauthorized in Laws 2022, Chapter 52, Section 148 to plan, design and construct a railroad quiet zone on Los Lentes road and Luscombe lane in Los Lunas in Valencia county may include planning, designing and constructing a railroad quiet zone on Gabaldon road in Belen in Valencia county. The time of expenditure is extended through fiscal year 2026.

     SECTION 254. SALAM ACADEMY BUILDING SYSTEMS IMPROVEMENT--CHANGE TO MANZANO MESA PICKLEBALL COURT CONSTRUCTION--CHANGE AGENCY--EXTEND TIME--SEVERANCE TAX BONDS.--The unexpended balance of the public education department project in Subsection 26 of Section 18 of Chapter 53 of Laws 2022 to purchase and install solar panels and to replace heating, ventilation and air conditioning units at Salam academy in Albuquerque in Bernalillo county shall not be expended for the original purpose but is appropriated to the local government division to plan, design, construct and equip pickleball courts near Manzano Mesa multigenerational center in Albuquerque in Bernalillo county. The time of expenditure is extended through fiscal year 2026.

     SECTION 255. BAHAST'LAH CHAPTER WATER LINE EXTENSION--EXTEND TIME--GENERAL FUND.--The time of expenditure for the Indian affairs department project in Subsection 44 of Section 70 of Chapter 81 of Laws 2020 to plan, design, construct, extend and repair a water line for the Bahast'lah chapter of the Navajo Nation in McKinley county is extended through fiscal year 2026.

     SECTION 256. EMERGENCY.--It is necessary for the public peace, health and safety that this act take effect immediately.

- 96 -